LEED v5
New Construction
Energy and Atmosphere
Fundamental Commissioning

NC-v5 EAp3: Fundamental Commissioning Required

LEEDuser overview

Explore this LEED credit

Post your questions on this credit in the forum, and click on the credit language tab to review to the LEED requirements.

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Intent

To improve energy performance and limit greenhouse gas emissions by verifying that systems are operating per the owner’s project requirements.

Requirements

Comply with ANSI/ASHRAE/IES Standard 90.1 commissioning requirements for building systems, controls, and the building envelope, with the following additional provisions:

  • All projects shall provide fundamental commissioning. Section 4.2.5.2 exceptions shall not apply.
  • The referenced version of Standard 90.1 with errata shall be:
    • 2019 or later for projects registered before January 1, 2028.
    • 2022 or later for projects registered on or after January 1, 2028.
  • By the end of the design development phase, the owner shall designate a commissioning provider (CxP) with experience completing commissioning on at least two projects of equal or larger scope and complexity.
  • In addition to the requirements of the applicable version of ASHRAE 90.1, the CxP shall:
    • In predesign or as early as possible, assist in the development of the OPR, reviewing and updating the OPR through design and construction. OPR must include HVAC, service water heating, power, lighting, other equipment (include on-site renewable energy), and envelope. 
    • During design, review the BOD for compliance with the OPR, and attend at least one meeting focused on mechanical, electrical, and plumbing, and one focused on envelope, which may be separate or combined, to discuss review comments and commissioning.
    • During construction, review submittals and substitutions for design deviations that impact the OPR, attend milestone meetings at 50% and 100% completion, and perform a sample review (minimum 10%) of completed contractor documentation for quality assurance/quality control. 
    • Occupancy/operations phase: Develop an ongoing commissioning plan. 
See all forum discussions about this credit »

Frequently asked questions

No results found
See all forum discussions about this credit »

What does it cost?

Cost estimates for this credit

On each BD+C v4 credit, LEEDuser offers the wisdom of a team of architects, engineers, cost estimators, and LEED experts with hundreds of LEED projects between then. They analyzed the sustainable design strategies associated with each LEED credit, but also to assign actual costs to those strategies.

Our tab contains overall cost guidance, notes on what “soft costs” to expect, and a strategy-by-strategy breakdown of what to consider and what it might cost, in percentage premiums, actual costs, or both.

This information is also available in a full PDF download in The Cost of LEED v4 report.

Learn more about The Cost of LEED v4 »

For full access, sign up now for LEEDuser Premium

Already a premium member? Log in now

Checklists

Step by step to LEED certification

LEEDuser’s checklists walk you through the key action steps you need to earn a credit, including how to avoid common pitfalls and save money.

For full access, sign up now for LEEDuser Premium

Already a premium member? Log in now

Documentation toolkit

The motherlode of cheat sheets

LEEDuser’s Documentation Toolkit is loaded with calculators to help assess credit compliance, tracking spreadsheets for materials, sample templates to help guide your narratives and LEED Online submissions, and examples of actual submissions from certified LEED projects for you to check your work against. To get your plaque, start with the right toolkit.

For full access, sign up now for LEEDuser Premium

Already a premium member? Log in now


Addenda

This credit has no LEEDuser summary

See all forum discussions about this credit »

Credit language

USGBC logo

© Copyright U.S. Green Building Council, Inc. All rights reserved.

Intent

To improve energy performance and limit greenhouse gas emissions by verifying that systems are operating per the owner’s project requirements.

Requirements

Comply with ANSI/ASHRAE/IES Standard 90.1 commissioning requirements for building systems, controls, and the building envelope, with the following additional provisions:

  • All projects shall provide fundamental commissioning. Section 4.2.5.2 exceptions shall not apply.
  • The referenced version of Standard 90.1 with errata shall be:
    • 2019 or later for projects registered before January 1, 2028.
    • 2022 or later for projects registered on or after January 1, 2028.
  • By the end of the design development phase, the owner shall designate a commissioning provider (CxP) with experience completing commissioning on at least two projects of equal or larger scope and complexity.
  • In addition to the requirements of the applicable version of ASHRAE 90.1, the CxP shall:
    • In predesign or as early as possible, assist in the development of the OPR, reviewing and updating the OPR through design and construction. OPR must include HVAC, service water heating, power, lighting, other equipment (include on-site renewable energy), and envelope. 
    • During design, review the BOD for compliance with the OPR, and attend at least one meeting focused on mechanical, electrical, and plumbing, and one focused on envelope, which may be separate or combined, to discuss review comments and commissioning.
    • During construction, review submittals and substitutions for design deviations that impact the OPR, attend milestone meetings at 50% and 100% completion, and perform a sample review (minimum 10%) of completed contractor documentation for quality assurance/quality control. 
    • Occupancy/operations phase: Develop an ongoing commissioning plan. 