Forum quick links
Minimum IAQ Performance Calculator - Multiple Zone and 100% OA
CI-2009 IEQp1:Minimum IAQ Performanceposted by Ron Dean on
I have difficulty filling out the Minimum IAQ Performance Calculator table for multiple zones.
Ventilation rates at unoccupied rooms
CI-2009 IEQp1:Minimum IAQ Performanceposted by Stacey Olson on
This project is in California, and ventilation rates comply with Title 24.
Switching from Appendix A to Table 6-3 to calculate Ev
CI-2009 IEQp1:Minimum IAQ Performanceposted by Edgar Arevalo on
I am using an old 62MZ calculator file to do comply with the IEQp1 prerequisite. However, after adjusting the ventilation rates for peak heating mode, Ev cannot be calculated on the spreadshe
Supporting interior AHU with no outside air supply.
CI-2009 IEQp1:Minimum IAQ Performanceposted by LEED Pro Consultant on
We are working in a project pursuing LEED-CI certification, and some of the base building AHU's were short on supplying air in order to meet the demand of lay-out spaces, so the interior HVAC desig
ASHRAE 62.1
CI-2009 IEQp1:Minimum IAQ Performanceposted by Mike D on
Clause 5..9 in ASHRAE 62.1 requires MERV 6 filters on all cooling coils or other surfaces. This will very much affect the energy efficiency of the systems.
Modification to base building systems
CI-2009 IEQp1:Minimum IAQ Performanceposted by Ben Hollon on
I feel like I've seen parts and pieces of this question in various posts but never asking it directly.
Project can't meet Outside Air Requirements
CI-2009 IEQp1:Minimum IAQ Performanceposted by Rob Hink on
We have a project which the outdoor air supply is limited from the base building HVAC system (out of our boundary) and we are not sure if the project will be able to meet the ASHRAE 62.1 requiremen
Multiple or Single Zone?
CI-2009 IEQp1:Minimum IAQ Performanceposted by Esteban Martinez on
Hello everybody We are working on a CI 2009 Office project with dedicated Fan Coil Units for each space. The FCU are located above the ceiling (inside the plenum).
Open Plan office served by 4 AHUs
CI-2009 IEQp1:Minimum IAQ Performanceposted by Michael Wahjudi on
Hi all, we received comments from reviewer that requesting the system computation should be separated for each system. Our development consists of few meeting rooms and open plan offices.