EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  Tristan Schwartzman  on 

If the audit was conducted in 2014 and we are submitting the LEED application in 2019, does the performance period start date need to be in 2014?

2
Editorial Director
BuildingGreen, Inc.
LEEDuser Expert
159 thumbs up
Wed Oct 2, 2019, 3:39 pm
2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Wed May 9, 2018, 3:28 pm

When to redo the ashrae energy audit for a re-certification.

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  Richard Klein  on 

When reading through the LEED re-certification guidelines it states that an ASHRAE energy audit must be done once every 5 years, however, it also states that the performance period is between

4
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Mon Mar 26, 2018, 9:10 pm
2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Wed Oct 11, 2017, 7:14 am

Paring down existing report

posted by  James Gray  on 
1
Wed Dec 22, 2010, 10:33 pm

System narrative

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  ESD Singapore  on 

Hi all, I am currently working on a retail mall that starts operating from 10am to 10pm.

1
Wed Jul 31, 2013, 3:52 pm

In house audit

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  Ryan Tinus  on 

I am interested in using our in house engineering staff to perform the ASHRAE level 1 audit required for this prereq, as well as the level 2 audit for c2.1.

1
Tue May 3, 2011, 9:06 pm

EBOM 2009 EAp1 L-9 upload document

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  James Doyle  on 

The credit template form for EBOM 2009 EAp1 on page 2 requests "Upload L-9. Provide a breakdown of total project building annual energy consumption by major end uses or applications.

1
Tue Jun 17, 2014, 1:06 pm
1
Fri Jul 30, 2010, 5:09 pm

Energy Usage Breakdown

EBOM-2009 EAp1:Energy Efficiency Best Management Practices
posted by  Jessica Long  on 

The book states that 24 hour load profiling data is "available from the utility company"? Is this a valid way to back into the total load usage data?

1
Tue Jun 19, 2012, 11:34 pm