Temperature and Humidity Monitoring During Flush

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Nancy Henderson  on 

Is it part of the requirement of this credit to monitor temperature and humidity in the space during the flush out - or is it sufficient to provide the temperature set points and calculate the resu

2
Mechanical Engineer
Integral Group
LEEDuser Expert
342 thumbs up
Tue Mar 13, 2018, 3:01 pm

phased flushing for hospital project

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Ed Clark  on 

Due to phasing plan the contractor will need to run AHU prior to completion of another phase of the project.

1
Fri Oct 21, 2011, 5:29 pm

Option 2 IAQ Testing - Schedule

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Anne-Claire BARBERI  on 

Hello, In the reference guide, it is written that for "Option 2 Air Testing", the test must be conducted after construction ends and within 14 days following occupancy.

1
Fri Jun 24, 2016, 9:52 am

Areas of question

posted by  Elizabeth Repin  on 
1
Wed Apr 21, 2010, 8:32 pm

flush-out documentation

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Alicja Bieszyńska  on 

Do we have to document flush-out somehow for the credit compliance? Is any report or declaration needed?

1
Wed Sep 26, 2012, 3:28 pm

IAQ Testing

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Brett Farbstein  on 

Can the Owner or GC do the IAQ test themselves ie be responsible for setting the test can and chain of custody to the lab?

1
Tue Jul 22, 2014, 11:18 am

Question on Selecting IAQ Test Locations

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Melissa Wrolstad  on 

I am working on a small ~6,500 sq. ft. LEED-CI office space.

1
Mon Nov 4, 2013, 4:26 am
1
Thu Jan 21, 2010, 1:02 am

IEQc3.2 VOC Testing

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  mark morehouse  on 

I have a 191,000 sf nc school that will require 11 sample points.

1
Mon Aug 13, 2012, 3:59 pm

Option 1: Full Flush-out Before Occupancy - Is there a Min. CF?

CI-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancy
posted by  Michelle Bracewell-Musson  on 

With Option 1, Path 1, we are expected to flush-out 14,000 cf/sf of outdoor air at 60 degrees temp. and 60% humidity min. Is there a minimum ventilation rate as with Path 2 which is 0.30 cf/min.?

1
Thu Sep 22, 2011, 3:37 pm