outdoor air rate for kitchens

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Adam Targowski  on 

I would like to ask if there's any requirement regarding outdoor air suplly to a kitchen located in an office area? In ASHRAE 62.1-2007 Table 6-1 a kitchen is not mentioned.

1
Fri Dec 21, 2012, 7:57 pm

Mech. exhaust fan required for a naturally ventilated project?

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Ron Dean  on 

I'm working in a small project with natural ventilation overall. Considering these 3 facts: 1. LEED states to comply with sections 4-7 of ASHRAE 62.1-2007. 2.

1
Tue Aug 26, 2014, 7:36 pm

Base building system

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Graham Langton  on 

Hi, To what extent does the base building system need to be entered into the VRP calculator?My CI project spaces is carried out space by space but that level of detail for other tenants isn't ava

0

Project can't meet Outside Air Requirements

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Rob Hink  on 

We have a project which the outdoor air supply is limited from the base building HVAC system (out of our boundary) and we are not sure if the project will be able to meet the ASHRAE 62.1 requiremen

1
Fri Aug 31, 2012, 5:44 pm

Supporting interior AHU with no outside air supply.

CI-2009 IEQp1:Minimum IAQ Performance
posted by  LEED Pro Consultant  on 

We are working in a project pursuing LEED-CI certification, and some of the base building AHU's were short on supplying air in order to meet the demand of lay-out spaces, so the interior HVAC desig

1
Fri Dec 21, 2012, 7:37 pm

ASHRAE 62.1

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Mike D  on 

Clause 5..9 in ASHRAE 62.1 requires MERV 6 filters on all cooling coils or other surfaces. This will very much affect the energy efficiency of the systems.

0

Modification to base building systems

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Ben Hollon  on 

I feel like I've seen parts and pieces of this question in various posts but never asking it directly.

0
1
Sun Mar 28, 2010, 1:54 pm

Multiple or Single Zone?

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Esteban Martinez  on 

Hello everybody We are working on a CI 2009 Office project with dedicated Fan Coil Units for each space. The FCU are located above the ceiling (inside the plenum).

1
Sun Jul 21, 2013, 4:56 pm

Open Plan office served by 4 AHUs

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Michael Wahjudi  on 

Hi all, we received comments from reviewer that requesting the system computation should be separated for each system. Our development consists of few meeting rooms and open plan offices.

1
Mon Jan 23, 2017, 3:01 pm