Commissioning Agent for project larger than 50,000sf
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Katrina Chong on
We are pursuing both EAp2 and EAc3 for our v2009 C&S project.
OPR Format - Tabular vs. Narrative
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Maya Karkour on
Dear all, Can the OPR be written in a tabular form, instead of a narrative, especially that we are not required to upload this? Thanks!
CxA and energy modelling
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Max Zayika on
Can energy modelling and fundamental + enhanced commissioning be done by the same company? Any conflict of interest in such setup?
Commissioning
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Karina Hanyzewski on
In a situation where the building undergoes tenant improvements before the shell construction is complete, does the commissioning work need to be adjusted to pick up the changes, even if they are t
Tenant area commissioning
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by sompoche sirichote on
Our project is an office building with 10 floors on the top are leased out as a hotel tenant and we are seeking for LEED CS certified. If the mechanical and electrical plant of the hotel are separa
Commissioning Agent Experience Template Form
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by nalat yulong on
The commissioning agent for our project indicated there is a LEED template he has completed in the past documenting his experience as an agent on similar projects and detailing his certifications.
Cx coordination with tenant move in
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Matt Humphreys on
What impact will the following two situations have on earning the fundamental commissioning prerequisite? 1.
CxA vs supervisor / PM
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Catharina B on
Hi On our project more than 50 000sq Owner hired a Project Manager whose responsibility is to supervise (e.g.
Commissioning building areas
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by gabriel Morales on
We have a process of commissioning CS 2009 , and we have a question: In the reference guide mentioned that 50,000 SF smaller projects the contractor could be the CxA , however the area of 50,00
What needs to be commissionined in a Major Renovation
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Donald Green on
We have a LEED v2009 CS Project - existing building major renovation. Most of the systems will not be touched and there will be the addition of a couple new mechanical units.