Commissioning Agent for project larger than 50,000sf

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Katrina Chong  on 

We are pursuing both EAp2 and EAc3 for our v2009 C&S project.

1
Sun Oct 26, 2014, 2:52 am

OPR Format - Tabular vs. Narrative

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Maya Karkour  on 

Dear all, Can the OPR be written in a tabular form, instead of a narrative, especially that we are not required to upload this? Thanks!

1
Mon Nov 21, 2011, 4:11 am

CxA and energy modelling

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Max Zayika  on 

Can energy modelling and fundamental + enhanced commissioning be done by the same company? Any conflict of interest in such setup?

1
Thu Nov 17, 2016, 3:35 pm

Commissioning

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Karina Hanyzewski  on 

In a situation where the building undergoes tenant improvements before the shell construction is complete, does the commissioning work need to be adjusted to pick up the changes, even if they are t

1
Mon Jun 30, 2014, 1:03 pm

Tenant area commissioning

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  sompoche sirichote  on 

Our project is an office building with 10 floors on the top are leased out as a hotel tenant and we are seeking for LEED CS certified. If the mechanical and electrical plant of the hotel are separa

1
Mon Nov 21, 2011, 2:18 pm

Commissioning Agent Experience Template Form

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  nalat yulong  on 

The commissioning agent for our project indicated there is a LEED template he has completed in the past documenting his experience as an agent on similar projects and detailing his certifications.

1
Thu May 31, 2012, 4:49 pm

Cx coordination with tenant move in

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Matt Humphreys  on 

What impact will the following two situations have on earning the fundamental commissioning prerequisite? 1.

1
Tue May 20, 2014, 6:47 pm

CxA vs supervisor / PM

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Catharina B  on 

Hi On our project more than 50 000sq Owner hired a Project Manager whose responsibility is to supervise (e.g.

4
Default Avatar
LEED AP BD+C
LEEDuser Basic Member
4 thumbs up
Tue Mar 8, 2016, 3:30 pm

Commissioning building areas

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  gabriel Morales  on 

We have a process of commissioning CS 2009 , and we have a question: In the reference guide mentioned that 50,000 SF smaller projects the contractor could be the CxA , however the area of ​​50,00

2
Chief Environmental Officer
Alpenglow Advisory
LEEDuser Basic Member
44 thumbs up
Wed Feb 24, 2016, 5:09 pm

What needs to be commissionined in a Major Renovation

CS-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Donald Green  on 

We have a LEED v2009 CS Project - existing building major renovation. Most of the systems will not be touched and there will be the addition of a couple new mechanical units.

3
Sr Project Manager / Operations Manager
Progressive AE
LEEDuser Basic Member
25 thumbs up
Mon Jan 11, 2016, 4:37 pm