Tenant Metering Questions

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Marina Andrade  on 

Hi, I'm working on a project that has many storage modules that will be occupied by tenants.

1
Thu Feb 13, 2014, 4:05 pm

applying only for EAc5.2 not EAc5.1

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Anna Bak  on 

Hi! Do you know if we can apply for EAc5.2 without applying for EAc5.1? The Investor doesn't want to pay for the model callibration, therefore we will not apply for EAc5.1.

1
Thu Jun 12, 2014, 2:27 pm

Leasable areas fed by the utility

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Ricardo Sá  on 

An office building is being certified under LEED C&S. All leasable areas will be fed directly by the utility.

1
Mon Aug 3, 2015, 1:21 pm

EA Credit 5.2: Tenant Submetering - Electricity

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Ian McCall  on 

Hello all, I am working on a large Core and Shell project composed of office spaces and commercial centre (in France). The commercial centre is 5 stories high and occupied by one single tenant.

1
Wed Jun 4, 2014, 11:52 pm

Could you explain the plan just one more time?

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Charles Nepps  on 

I am still a bit unclear about the the M&V - Tenant Submetering documentation.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Thu Dec 22, 2016, 4:12 pm

>75% M&V Template Requirement

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Martin Meehan  on 

Dear all, Our project recently received the comment below which appears to require an Option B or D 'template' to be submitted with our plan if a tenant is to take 75% or more of the building spa

8
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Fri Sep 30, 2016, 4:34 pm

Metering Requirements

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Ciaran McCabe  on 

Hi, I am working on a commercial project that consists of retail units on the ground floor and offices on the levels above.Currently the base build does not show and ten ant metering for the retail

3
Director
Passive Dynamics Sustainability Consultants
LEEDuser Basic Member
12 thumbs up
Wed Sep 28, 2016, 9:59 pm

Corrective Actions and Sub-metering

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Jatuwat Varodompun  on 

For the submetering, we can just provide the box that allow the tenant to install the meter, right?

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Wed Aug 31, 2016, 11:08 pm

Tenant is installing the entire energy systems at the building

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Michael Wahjudi  on 

Hi all, we have building where the tenant is installing the entire energy related system (ACMV, lighting, etc). The landlord only provide land and structural of the building.

3
Fri Aug 5, 2016, 10:43 pm

Single tenant in building pursuing Core & Shell

CS-2009 EAc5.2:Measurement and Verification—Tenant Submetering
posted by  Dave Hubka  on 

The building is pursuing C&S certification and has a perspective tenant that may fit out the entire space.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4461 thumbs up
Thu Nov 5, 2015, 4:44 pm