Exempting Space for LEED EBOM

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Michael McPheron  on 

Our building includes offices attached to a manufacturing facility by a hallway and kitchen area. The initial goal was to just get the offices and kitchen area LEED certified for EBOM.

1
Sat Mar 8, 2014, 3:36 am

Campus road

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Susan Di Giulio  on 

We have a project on a university campus. The university maintains the roads on the campus, although there is public access 24/7.

1
Sat Nov 28, 2015, 1:57 pm

Determining Site Boundary on Renovations/Additions

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Andrew Buck  on 

We are working on a Hotel that is both a renovation and major new construction.

1
Tue Aug 9, 2016, 5:58 pm

Public R.O.W.

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  James Wieben  on 

I am working on a project where the building footprint occupies the entire site. The project is constructing completely new surface amenities inthe right-of-way, including landscaping.

1
Wed Oct 31, 2012, 4:31 pm

Identifying LEED boundary to exclude portion of project

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Kristen Dotson  on 

The registered project includes commercial core and shell space with an adjoining housing tower which will be scored under the Evergreen Sustainable Development Standard.

1
Sat Mar 8, 2014, 3:37 am

LEED Project Boundary - Football Stadium

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Lisa VandeVoort  on 

Our project is a new football stadium on a college campus. Is it acceptable to limit our project boundary to include just the pressbox / suite tower?

0

LEED Boundary and Non-contiguous reconfigured areas

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Aaron Ketner  on 

Our project is currently registered under NC 2009. This 66,500sf project consists of a new classroom addition to an existing 53,000sf building, which achieved LEED silver under NC 2.2.

0

Reasonable Site Boundary for Lighting

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Carol Liebst  on 

I am working on a school on an army base - to be LEED Silver (2009). I want to be I am correctly establishing the lighting boundary.

1
Thu Mar 21, 2013, 2:43 pm

Project of 2 buildings in one territory

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Laurence Theriault  on 

I am working on a project who has two buildings in his land, but only one of them (an office building) will be in the process of becoming LEED NC.

1
Tue Apr 30, 2013, 11:05 pm

Redrawing Project Boundary AFTER Initial Review

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  C.M. G.  on 

Hello, We are currently preparing our project for final review, and realized that that we drew our project boundary in such a way that disqualifies us from SSc8.

1
Mon Dec 23, 2013, 7:31 pm