existing parking garage in the LEED project boundary

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  yanghee pierce  on 

I am working on a project that is a part of campus. This project will be located next to a 4-story existing parking garage shared by other adjacent non-LEED certified buildings.

1
Tue Apr 30, 2013, 11:02 pm

LEED NCv3 Project Boundary in 3 Dimensions

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Sara Goenner Curlee  on 

Hello, I am reposting this question, hoping to get a response. It was under PIf2, but maybe this is the better area to post it.

1
Sat Dec 21, 2013, 3:41 am

LEED Site boundary – underground parking

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Florian Schmidtchen  on 

Hello all, We are working on a project with 2 stories for underground parking. About the half of the parking space is built for building users as required by local zoning requirements.

0

LEED Project Baundary

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Paula Hernandez  on 

Hi, We have a 16 story building which is going under major renovation. The new Owner wants to get the building certified as C&s. The issue is that the ground floor will be shared with a Hotel.

0

Public R.O.W.

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  James Wieben  on 

I am working on a project where the building footprint occupies the entire site. The project is constructing completely new surface amenities inthe right-of-way, including landscaping.

1
Wed Oct 31, 2012, 4:31 pm

Underground car parking

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  BH .  on 

Hi, we are dealing with new LEED hospitality project. The project will be constructed in two stages (two towers), with common parking under both of them constructed in the first stage.

1
Thu Mar 21, 2013, 2:29 pm

LEED Project Boundary for a Train Station

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Michael G  on 

Hi all, I have an issue properly defining the project boundary for a Train Station on a large overall site which includes the station, outdoor plaza, train platforms, large parking lots, a substati

1
Tue Nov 5, 2013, 4:43 pm

Exempting Space for LEED EBOM

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Michael McPheron  on 

Our building includes offices attached to a manufacturing facility by a hallway and kitchen area. The initial goal was to just get the offices and kitchen area LEED certified for EBOM.

1
Sat Mar 8, 2014, 3:36 am

Campus road

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Susan Di Giulio  on 

We have a project on a university campus. The university maintains the roads on the campus, although there is public access 24/7.

1
Sat Nov 28, 2015, 1:57 pm

Determining Site Boundary on Renovations/Additions

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Andrew Buck  on 

We are working on a Hotel that is both a renovation and major new construction.

1
Tue Aug 9, 2016, 5:58 pm