BPDO Material Ingredients: required to report material cost if pursuing Option 1?
CI-v4 MRc5:Building product disclosure and optimization - material ingredientsposted by Adam Weiss on
Hello, if we are pursuing option 1 for MRc5 (20 compliant products from at least 5 manufacturers), are we required to report the cost of each material?
How many sample locations for measurement?
CI-v4 EQc9:Acoustic performanceposted by Brian Salazar on
I am looking to take mic measurements of the ambient noise in our space to provide a baseline for HVAC Background Noise. The Acoustic performance Calculator specifies the following:
Do thermofusers count for controllability?
NC-v4 EQc5:Thermal comfortposted by Alaina Ladner on
Would thermofusers satisfy the requirements of controllability for this credit? I seem to have confirmation from LEED 2009, but don't really see a clear direction under v4 or v4.1
Solar energy still doesn't count toward to minimum energy reduction in v4?
NC-v4 EAp2:Minimum energy performanceposted by Michael on
My understanding is that LEEDv4.1 allows on-site renewables to count toward compliance in the prerequisite.
MRc4, Option 3 - Product manufacturer supply chain optimization
NC-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by Filippo Weber on
I would like to ask for a clarification regarding the documentation required for credit MRc4 – BPDO Material ingredients , Option 3 “Product manufacturer suppl
Calculate U-value of exterior wall
NC-v4 EAp2:Minimum energy performanceposted by Michael on
Regarding the U-value of the exterior wall in the proposed model, I see the LEED calculator provided a hint "Proposed construction assembly U-factor should be as-designed and consistent with A
Commercial Interior Project Information - Site Plan
CI-v4 MPR3:Must comply with project size requirementsposted by Edgar Arevalo on
I'm working on a commercial interior project for LEED v4 rating system. Under the Project Information form, it asks for site plan. What would I provide for a project located on the
Target Finder outside the US - Project in Europe
NC-v4 EAp2:Minimum energy performanceposted by Worood Shbeikat on
Hi, Is it true that a project outside the US (located in Europe) does not necessarily have the target finder results? for LEED accreditation?
Water test location
EBOM-v4 WEc3:Cooling tower water useposted by Clive Lacey on
Water test for Cooling tower should be done on site?