Total Site Paving Area
NC-v4 SSc5:Heat island reductionposted by Maria Perzon on
I am not sure about the definition of "Total Site Paving Area". I have a already developed site with a building that is to be majorly rebuilt. Could I use the old site paving area as my reference?
Demand response infrastructure associated costs
NC-v4 EAc4:Demand responseposted by Julio Fernandez Amodia on
Hi there,
I am currently assessing the feasibility of this credit. As per now I am aiming for Case 2. since there is no know DR program available.
RECs - projects outside the U.S.
NC-v4 EAc7:Green power and carbon offsetsposted by Camila Rossini on
Could anyone help me verfify if the following understandig is correct? Tks!
Perimeter area calculation
Healthcare-v4 EQc7:Daylightposted by Priscillia Champagne on
Does anyone know if the perimeter area to be used for Healthcare projects excludes from the calculations the non-regularly occupied space within that perimeter, or do we need to include the whole a
Fire Treated Plywood - how to document PS 1 or PS 2 standard?
NC-v4 EQc2:Low-emitting materialsposted by Erin Holdenried on
Anybody have advice on how to document a plywood product is manufactured to PS-1 or PS-2 standard for fire treated products? I am getting pushback from GBCI for Hoover Pyro-guard products.
Data Center load for Renewable Energy design
Data-Centers-NC-v4 EAc2:Optimize energy performanceposted by Instra Ingenieros on
We have a question about the energy simulation of a Data Center. We have completed the v4 Minimum Energy Performance Calculator introducing full IT and initial IT loads.
No-Smoking Signs - Warehouse Loading Dock & Overhead Doors
NC-v4 EQp2:Environmental tobacco smoke controlposted by Mel K on
Hello,
Are no-smoking signs required to be installed for loading dock & overhead doors?
Thank you.
Exclusive Parking Location
NC-v4 LTc8:Green vehiclesposted by Sofia Barahona on
The preferred parking spaces of green vehicles has to be, according to Reference Guide, on the shortest walking distance to the main entrance.
Exempt from Indoor Water Efficiency pre-requisite?
NC-v4 WEp2:Indoor water use reductionposted by Lawrence Lile on
We have a project that includes no bathrooms, kitchens, or other indoor water use. There is an industrial process that uses water, which we will address separately. Can we claim exempti