Forum quick links
LTc5 - Heat Island Reduction - examplary performance
NC-v4 SSc5:Heat island reductionposted by Maria Peralta on
Hello, I have a doubt about the examplary performance of this credit.
Option 3 without tenant meters
EBOM-v4 EAc4:Optimize energy performanceposted by Omar Elrawy on
Hi All,
We are conducting feasibility study on an existing building in which we are changing chillers. And we are planning to comply under Option 3: Historical Data
Option 3 without tenant meters
NC-v4 EAp2:Minimum energy performanceposted by Omar Elrawy on
Hi All,
We are conducting feasibility study on an existing building in which we are changing chillers. And we are planning to comply under Option 3: Historical Data
USGBCs online web-based reference guide
NC-v4 MPR1:Must be in a permanent location on existing landposted by Kavita Karmarkar on
Posting this question here since it does not belong to any credit in particular.
Non-certified buildings in LEED boundary
NC-v4 MPR2:Must use reasonable LEED boundariesposted by marty seese on
I have a project that is all new construction. There are 3 buildings on the site. The main building which is what the owner wants to be LEED Certified. Another building is a shed building.
Interpretation of text relating to Envelope
NC-v4 EAp1:Fundamental commissioning and verificationposted by Keith Fahy on
Hi, see here an extract from the Reference Guide: "The envelope must be covered in the OPR and BOD, but full envelope commissioning is not required unless the project team pur
Disinfectants with EPA Registration No. and on List N: Disinfectants for Coronavirus (COVID-19)
EBOM-v4 EQc7:Green cleaning - products and materialsposted by DINGTIAN OU on
Few green disinfectants (e.g. Green Seel, UL or EPA Safer Choice Standard certified) are available in Hong Kong market.
Our clients proposed two commonly used disinfectants:
District cooling chilled water
CS-v4 WEc2:Indoor water use reductionposted by Dina El-Sady on
If the project is served by a district cooling plant outside LEED project boundary , does the chilled water count as process water and needs to be included in water efficiency calculations?
All-Gender Restrooms - Verticality (Locate on all levels or selected levels?)
NC-v4 INc1:Innovationposted by Vijitha Mammen on
We are working on a post-secondary education project incorporating both gendered and all-gender restrooms.