Child care center - students included in occupany?

NC-v4 LTc6:Bicycle facilities
posted by  Maddie Spinski  on 

We are building a child care center for toddlers age 0-5, therefore we did not register under New Schools as the project does not include grades K-12.

1
Thu Nov 12, 2020, 4:25 pm

Dedicated Kitchen Exhaust

NC-v4 EQp1:Minimum indoor air quality performance
posted by  colleen soden  on 

We have a low rise (4 story) multifamily residential project considering LEED v4 BD+C in Boston.

4
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Wed Nov 11, 2020, 10:59 am

EAc6 Enhanced Refrigerant Management

NC-v4 EAc6:Enhanced refrigerant management
posted by  Roshni Lad  on 

Hello,

I am working on a New Construction project - a community center, certifying under LEED v4. 

2
Project Manager
VCA Green
LEEDuser Basic Member
1 thumbs up
Tue Nov 10, 2020, 9:58 pm

Core and Shell without plumbing

CS-v4 WEp2:Indoor water use reduction
posted by  Karl Heitman  on 

I would like to confirm that if the developer doesn't install any plumbing fixtures for his core and shell industrial project, this prerequisite is automatically met.  Appreciate your answer i

3
Default Avatar
Sr. Sustainable Design Specialist
HOK
LEEDuser Basic Member
1 thumbs up
Tue Nov 10, 2020, 9:06 pm

IT Room Space Cooling

NC-v4 EAc3:Advanced energy metering
posted by  Mark Zoeteman  on 

Reference Guide states under Data Center heading: IT energy consumption, as measured from an uninterruptible power supply (UPS) output meter, should be metered separately from non-IT equipment, suc

4
Tue Nov 10, 2020, 4:47 pm

View of sky via skylights in a warehouse

Warehouses-NC-v4 EQc8:Quality Views
posted by  Agnieszka Rylska  on 

Can we include the view of the sky via skylights in the warehouse for the purpose of this credit?

1
Wed Nov 11, 2020, 9:54 pm

off-site parking

NC-v4 SSc5:Heat island reduction
posted by  Tristan Roberts  on 

We have added an important FAQ to this credit: "How should we account for off-site parking under this credit?"

See our FAQ for the answer!

2
Sustainability Project Manager
Atkins
LEEDuser Basic Member
59 thumbs up
Fri Nov 6, 2020, 6:37 pm

LEED Certification for Mixed-Use Office and Residential

CS-v4 MPR3:Must comply with project size requirements
posted by  Van Jomel Garcia  on 

We have a project composed 60 floors, 1st-40th floor is office (12-40 floors leasable) and 41st-60th floor will be residential. In relation to the subject above, is it also possible to pu

1