2019 GreenTag Product Health Declaration (PhD)

EBOM-v4 EQp3:Green cleaning policy
posted by  Jutta Berns  on 

I came across a 2019 press release by Global GreenTag advising that the Global GreenTag PhD, Materials Transparency Certification Program is as of 2019 recognised by LEED and USGBC. 

1
Wed Dec 23, 2020, 12:57 am

No Cooling Tower - Baseline system categorization

NC-v4 WEc3:Cooling tower water use
posted by  Michelle Bombeck  on 

According to the Appendix G, our building does not fall into the allowable project type for System 7 or 8 but only because Appendix G indicates that the building has to be more than 5 stori

1
Mon Aug 10, 2020, 12:31 pm

Project Boundaries - Different Certifications, Different Towers, But Common Retail Podium & Basement

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  ARDOR GREEN  on 

Given the number of questions already posed on project boundaries, I hesitate to post this, but I'm still stumped. 

1
Tue Jul 28, 2020, 6:14 pm

Biodigestion process instead of composting

ND-Plan-v4 GIBc16:Solid waste management
posted by  LEED Pro Consultant  on 

We are trying to achieve the GIB - Solid Waste Management.

 

1
Mon Jul 27, 2020, 3:53 pm

Tolerance within the achievement of the criteria due to different affectations

NC-v4 EQc7:Daylight
posted by  Audrey LEDESERT  on 

Hi,

I'm working on a project with administration affectation and some commercial surfaces on the groundfloor (surface < 40% of the total project surfaces).

1
Mon Jul 27, 2020, 12:52 pm

Water-resistant flooring

Homes-v4 MRp2:Durability management
posted by  Alec Luong  on 

The credit states to "use water resistant flooring; do not use carpet." Is there a specific list of what LEED considers to be water resistant flooring?

1
Wed Jan 27, 2021, 6:24 am

Requirements for LEEDv4 BD+C Tenant Guidelines

NC-v4 MPR2:Must use reasonable LEED boundaries
posted by  Helene Lefkowitz  on 

I am working on a project that will have incomplete spaces that will be finished by tenants.

3
Sustainability Consultant
Ambient Energy
LEEDuser Basic Member
11 thumbs up
Fri Jul 24, 2020, 4:11 pm

COVID-19 Impacts

NC-v4 MRc5:Construction and demolition waste management
posted by  Joshua Mauldin  on 

I'm working on a university project and was just notified by our contractor that from February to June their waste hauler took all waste to landfill due to concerns about their employees being expo

1
Thu Jul 23, 2020, 11:18 pm

Surrounding density question for downtown Houston

CI-v4 LTc2:Surrounding density and diverse uses
posted by  Anna Kaelin  on 

Hello,

I am working on a retail store project in downtown Houston. The project is in the mall and I am looking for some help with this credit.

1
Fri Jul 31, 2020, 1:39 pm