Does the LCA must cover the 100% of building envelope and structural elements?

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Sara BENLOUBA  on 

To earn the 3 points on this credit, Question 1: Do I need to know life cycle analysis for 100% of my structural and envelope products? Even small products like tightness, ...?

4
Default Avatar
Green building manager
Confidential
LEEDuser Basic Member
13 thumbs up
Fri Oct 18, 2019, 8:15 am

Can a project have a different CxA for Fundamental and Enhanced Commissioning?

CI-v4 EAc1:Enhanced commissioning
posted by  Renee Shirey  on 

Our project went forward with Fundamental Commissioning using a member of the Engineering firm (disinterested party, not involved in any way with the design/engineering/construction of the building

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Oct 17, 2019, 8:48 pm

construction indoor air quality management plan

NC-v4 EQc3:Construction indoor air quality management plan
posted by  Anushka Singh  on 

Why was the construction IAQ management during construction and before occupancy from LEED 2009 combined to one credit Construction Indoor Air quality Management Plan in LEED v4?

1
Thu Oct 17, 2019, 4:28 pm

Whether or not to include certain existing fixtures within the area of work

CI-v4 WEp1:Indoor water use reduction
posted by  Bo White  on 

Our area of work includes portions of the first and second floors of a university library in California. On the first floor, only bathrooms are included.

2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Wed Oct 16, 2019, 11:43 pm

Standard bus stop - weekday vs weekend

NC-v4 LTc5:Access to quality transit
posted by  Felicia Ridgeway  on 

Can a standard bus stop count if it is within 1/2 mile of the project entrance, or is  a standard (non rapid) bus stop only allowed to count towards the 1/4 mile distance credit?  

5
Wed Oct 16, 2019, 9:59 pm

Occupant Comfort Survey

NC-v4 INc1:Innovation
posted by  Leanne Conrad  on 

Is there a minimum duration after occupancy you must wait to conduct the occupant comfort survey?

11
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Wed Oct 16, 2019, 7:48 pm

Space types and visitors to be surveyed

EBOM-v4 LTc1:Alternative transportation
posted by  Jorge Lopez de Obeso  on 

Hi, in an offices building visitors must be surveyed? The building has sporadic events in common spaces and the visitors rate is irregular.

1
Thu Oct 24, 2019, 5:29 pm
2
Wed Oct 16, 2019, 2:46 pm

LEED V4 ID+C

Retail-CI-v4 EAp2:Minimum energy performance
posted by  Neeraj Sharma  on 

The Project is a small office of area around 360 Sq.m in huge building of area around 7400 sq.m? The office building is served by central chiller & no heating.

0

Mandatory Provision for Lighting Controls C&S

CS-v4 EAp2:Minimum energy performance
posted by  Sofia Barahona  on 

We are currently working on a LEED Core and Shell v4 office building on Santiago, Chile.

1