NC-v4 EQc2:Low emitting materialsposted by Kristen Magnuson on
Does the USGBC accept products that have been tested for emissions in accordance with CDPH v1.2 (2017) for compliance with the low-emitting materials credit?
Envelope Cx - whole-building air leakage testing
NC-v4 EAc1:Enhanced commissioningposted by Julien Richard on
Is it acceptable if the air leakage testing is done by a subcontractor of the general contractor when all the other aspect of the envelope commissioning are done by an independant CxA ?
Emergency fire ventilation fans (motors) - Section 10.4.1
NC-v4 EAp2:Minimum energy performanceposted by Luis Andrade on
Hi,
Pilot Credit 87 – Verified Construction & Demolition Recycling Rates
CI-v4 INc1:Innovationposted by Bonny Gray on
We have submitted for Pilot Credit 87 - Verified Construction & Demolition Recycling Rates. We received the following comments:
Provide the following:
Stormwater Management in a project without pre-existing infrastructure
NC-v4 SSp1:Construction activity pollution preventionposted by Amine Zeidane on
Hello,
I'm working on a mixed-use tower construction project in Morocco.
LEED v4 Low Emitting Materials - Consistancy with testing methods
CS-v4 EQc2:Low emitting materialsposted by Estra Marku on
Do all of the adhesive/sealant products used on our LEED v4 cs project need to be consistent with one testing method?
Rule 1113 and 1168
Homes-v4 EQc7:Low-emitting productsposted by Xavi Ramon on
Can somebody confirm if the limits listed in rule 1168 (adhesives and sealants) and rule 1113 (paints and coatings) will be accepted for wet applied products in LEED v4 EQc7?
Materials inside the building
NC-v4 MRc1:Building life-cycle impact reductionposted by Konstantina Kalliakoudi on
Hello,
In my understanding the credits:
Building Life Cycle Impact Reduction
Building Product Disclosure and Optimization - EPD
Design Temperatures in Cooling and Heating - Must they differ 5 oF?
NC-v4 EAc2:Optimize energy performanceposted by Konstantina Kalliakoudi on
Hello to all,
When I am building the proposed building in my energy model has the design temperature in Cooling differ from the design temperature in Heating +5 oF?