Thermal Comfort Ranges

NC-v4 IPc1:Integrative process
posted by  Danilo Ilic  on 

The part "Assess Thermal Comfort Ranges" is not very clear for me.

1
Tue Oct 16, 2018, 5:32 pm

Food production in a Business District?

ND-Plan-v4 NPDc13:Local food production
posted by  Sareet Benayahu  on 

Hi. our LEED ND Plan project is for a business and retail sector, with congress halls and hotels. no residential units are planned.

0

existing trees to remain, but not greenfield

NC-v4 SSc2:Site development - protect or restore habitat
posted by  emily reese moody  on 

Our project is building adjacent to an existing building, and will connect to it via a pedestrian bridge. Between the two buildings are several existing, older trees that are required to remain.

1
Fri May 24, 2019, 3:05 pm

Differences between design phase and construction phase

NC-v4 MPR3:Must comply with project size requirements
posted by  JORDI CASTELLANO  on 

hello everyone,
our project has achieved the design phase of LEED review.

1
Mon Oct 15, 2018, 7:48 pm

Kitchen faucet nominal flow rate vs maximum flow rate

CI-v4 WEp1:Indoor water use reduction
posted by  shashank gangil  on 

We are doing a CI project in Hong Kong and going to select a kitchen faucet for installation in the pantry.

2
Sat Oct 13, 2018, 12:04 am

thinner use for cleaning purposes

CS-v4 EQc2:Low emitting materials
posted by  monica castro urbina  on 

The construction team want to know if the thinner used to clean the formwork for concrete slabs in the post-tensionnnig method have to comply with the VOC's limit required in the SCAQMD rule 1143?

0
4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Oct 11, 2018, 3:37 am

LEED Interpretation 10480

NC-v4 EAp2:Minimum energy performance
posted by  susan eguia  on 

Hi,

Is anyone here aware about LI 10480 requirements?

Appreciate sharing information please.

thanks,

Susan

 

1