Garage Demand Control Ventilation
NC-v4 EAp2:Minimum energy performanceposted by Charalampos Giannikopoulos on
If attempting to make use of LI 10371 for garage demand control ventilation how should the proposed model be differentiated from baseline to take advantage of CO sensors?
Cooling Tower drift eliminator - standards for processes
NC-v4 WEp2:Indoor water use reductionposted by Dionisio Franca on
We checked the drift eliminator specs with the manufacturer selected for our project and they told us that that their draft eliminators reduce drift to 0.05% only.
IEQ 0 VOC General Emissions Test Needed?
NC-v4 EQc2:Low emitting materialsposted by Jenelle Shapiro on
If any wet applied product is shown to have 0 VOCs, does it still need a general emissions evaluation?
Safe Paths of Travel in rural areas
Schools-NC-v4 LTc4:Surrounding density and diverse usesposted by Lou Niles II on
Hello has anyone seen a path or strategy for achieving credits that require safe paths of travel in rural areas or unincorporated areas?
What happened to less than or equal to?
NC-v4 EQc2:Low emitting materialsposted by Hannah Fleck on
I am running into an issue that a Low VOC PVC Solvent Cement lists the VOC requirement as 510g/L.
Could you confirm the attached cd/m2 results?
NC-v4 EQc6:Interior lightingposted by SSN Energy Model on
Hi,
Greeting!
Achieving the certified level to earn RP credit points?
NC-v4 RPc1:Regional priorityposted by Manuelle Croft on
With the LEED Canada 2009 versions, projects had to achieve the certified level prior to ean the Regional priority credit (RPc)points.
Crosswalk with PEER?
NC-v4 INc1:Innovationposted by emily reese moody on
I have a project that is located on a campus that earned PEER certification, and the client is asking how we can incorporate that as a benefit for our project, which is fed through the energy syste
Response rate
EBOM-v4 LTc1:Alternative transportationposted by zakir hossain on
How response rate effect in calculating transportation performance score?
Option 3. design for flexibility- Acessible ceiling system
CI-v4 MRc2:Interiors life-cycle impact reductionposted by Lara Branco on
The project I'm working on will leave all the ceiling infrastructure apparent, without the use of ceiling tiles (except a few acoustic panels). Therefore all the lighting, plumbing, etc.