Documenting the calculation of 40% or more is achieved

CI-v4 LTc5:Reduced parking footprint
posted by  Keith Lam  on 

How do we justify the percentage reduction is more than 40%, is there some sort of documentation required to demonstrate our project is not utilizing parking spaces that are allocated on the&n

2
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Fri May 25, 2018, 10:12 pm

Round up or down for weekend daily trip average?

NC-v4 LTc5:Access to quality transit
posted by  Danielle Waters  on 

The project has 16 trips Saturday and 13 trips Sunday, and the average is 14.5 [(16+13)/2].

Can I assume rounding up to 15 daily trips for the entire weekend?  

4
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Fri May 25, 2018, 4:08 pm

Inspection reports vs photos?

NC-v4 EQc3:Construction indoor air quality management plan
posted by  Erin Holdenried  on 

In v2009, inspection reports were sufficient documentation to confirm the implementation of the IAQ Mgmt Plan.  Is this still acceptable?  The LEED v4 reference guide only mentions photog

1
Thu May 31, 2018, 6:01 am

Is there a stormwater management sample document/template for LEED v4?

CS-v4 SSc4:Rainwater management
posted by  Qidi Jiang  on 

I noticed that the sample document provided in the documentation toolkit is applicable to LEED v2009, and not sample document for LEED v4 is available. 

0

LEED Interpretation 10231 still valid for v4?

NC-v4 SSc2:Site development - protect or restore habitat
posted by  CT G  on 

LEED Interpretation 10231 required a vegetated roof to be an intensive roof system, where the depth of the growing medium is 6 inches or more, and with at least six varieties of sedu

1
Tue May 29, 2018, 5:26 pm

Manage Runoff from Entire Site Requirement

NC-v4 SSc4:Rainwater management
posted by  Karina Lairet  on 

Per the USGBC Guide, it says that the project must manage rainwater runoff from the entire site within the project boundary.

1
Thu May 24, 2018, 3:11 pm

Gender Neutral toilets

NC-v4 WEp2:Indoor water use reduction
posted by  Jude Chakraborty  on 

Hello, we are working on an University project which has a directive on Gender Neutral toilets  which means there are no urinals in the building.

5
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Wed May 23, 2018, 11:15 pm

Room Geometry Adjustment - Baseline Lighting Power Increase

NC-v4 EAp2:Minimum energy performance
posted by  Luis Andrade  on 

Hi,

When modeling the Baseline's lighting power using the Space-by-Space method, may I icrease the Baseline's power by section 9.6.3 (Room Geometry Adjustment) by 20% ( if applicable)?

1
Thu May 24, 2018, 1:44 pm