SSp2 Environmental Site Assessment

Schools-NC-v4 SSp2:Environmental site assessment
posted by  Karly Michalowski  on 

I have a LEEDv4 for Schools project but is focusing on the interior restoration of the building and not site. Is Phase I ESA required for just interior restoration of the building?

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed May 16, 2018, 2:47 pm

Not eligible if no non-potable water?

CI-v4 IPc1:Integrative process
posted by  emily reese moody  on 

It appears that a project may not be eligible for the 1 point associated with the Water Related System if their building(s) do not offer non-potable water sources. Is this correct?

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed May 16, 2018, 2:01 am

Using CBECS 2012 Data for Estimating Energy Consumption

CI-v4 EAp2:Minimum energy performance
posted by  Oliver Bate  on 

I have multiple office projects where there is no consumption data available as the tenants are new to the building- we are going with Option 2 Minimum Energy Performance. 

13
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed May 16, 2018, 12:18 am
3
Default Avatar
LEED Coordinator/Construction Administrator/Business Development
Building Solutions Group, Inc.
LEEDuser Basic Member
47 thumbs up
Tue May 15, 2018, 11:28 pm
2
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Tue May 15, 2018, 9:57 pm

General Emission Evaluation and VOC Content for signage

CI-v4 EQc2:Low emitting materials
posted by  Gabriela Mena   on 

We are documenting a LEED/WELL project and we want to know if we must include the certification for the signage (branding, emergency exit, etc.) because we do not know in which category it should b

1
Mon May 21, 2018, 7:30 pm

Retro-commission an existing PV array?

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Deborah Lucking  on 

Our project is a county-owned building which will utilize renewable energy from an existing, adjacent, county-owned PV farm.

1
Wed May 16, 2018, 1:05 pm

Multiple CxAs?

NC-v4 EAc1:Enhanced commissioning
posted by  LUCY WILLIAMS  on 

Have any project teams had success using two different commissioning agents from two different entities in order to perform commissioning services on their project?  For example, can the

1
Tue May 15, 2018, 2:19 pm

Treatment Requirements

NC-v4 SSc4:Rainwater management
posted by  Annie Levan  on 

Hello,

Can someone please clarify the treatment requirements for various storm water strategies? A few example strategies are as followed:

0

Percent of Occupants

NC-v4 WEp2:Indoor water use reduction
posted by  Amy Ruffino  on 

On the Reduction Calculation spreadsheet, how should the "Percent of Occupants" be filled out for kitchen sinks or urinals?

11
Architect - Cx Provider - Building Performance Specialist
GLHN Architects & Engineers
LEEDuser Premium Member
25 thumbs up
Mon May 14, 2018, 9:17 pm