Shower location
NC-v4 LTc6:Bicycle facilitiesposted by Thu Nguyen on
This credit requires that "Provide at least one on-site shower with changing facility for the first 100 regular building occupants and one additional shower for every 150 regular building occupants
Multifamily Setpoints and Equipment Load
NC-v4 EAp2:Minimum energy performanceposted by Cory Duggin on
Are we required to use the equipment loads and setpoints from the Energy Star Multifamily High Rise Simulation Guidelines? I found that it is referenced by LEED for Homes, but I haven't found
How the fan efficiency W/cfm and pump efficiency W/gpm is decided in Ashrae 90.1?
CS-v4 EAp2:Minimum energy performanceposted by Homer Wang on
Where or which book we can find about how the fan efficiency W/cfm and pump efficiency W/gpm is decided in Ashrae 90.1 just like what type building or how large build is considered and how long duc
default visitor count for retail projects
Retail-NC-v4 LTc6:Bicycle facilitiesposted by Gail Napell on
we're doing a C+S with a retail lease space. How do we determine the retail visitor count for this credit, WE, etc.? i thought i saw this in v2009 but now i can't find it - can someone
Warehouse baseline system
CS-v4 EAp2:Minimum energy performanceposted by Instra Ingenieros on
Dear all,
Sharing Building-Level Energy Metering Data
NC-v4 EAc3:Advanced energy meteringposted by Francis Hernández on
We have a LEED v4 project for the Corps of Engineers that is connected via the local installations BMS to a remote location for managing the buildings energy systems. The meters and submeters
Compliant laboratory and medical equipment
NC-v4 WEc2:Indoor water use reductionposted by LEED Pro Consultant on
For equipment such as steam sterilizer and sterile process washer, the requirement mentions liters/DIN tray, does the tray has to be any specific measure?
Lack of Sunday bus service
NC-v4 LTc5:Access to quality transitposted by Karen Joslin on
I believe the intent of the emphasis on some level of weekend service means both Sat and Sun. If there are 0 trips on Sunday we cannot average with the high number of Sat trips can we?
Demolition Waste for entire building vs area designated to be LEED Certified.
CI-v4 MRp2:Construction and demolition waste management planningposted by Timothy Hillhouse on
We are renovating a 84,000 sqft warehouse and only LEED Certifying a portion of it 9865 sqft. Should all the construction waste & recycling only be calculated for the small area being cer
EPD as an alternative approach to comply with Option-4 requirements
NC-v4 MRc1:Building life-cycle impact reductionposted by Osman on
Hi all,
Is it acceptable to quantify for the impact measures in the proposed building using EPD?
Thank you so much for your support,
Osman