Automatic Receptacle Control
CI-v4 EAp2:Minimum energy performanceposted by Erik Camacho on
EAp2 has an mandatory ASHRAE requirement (90.1-2010, Section 8.4.2 Automatic Receptacle Control) requiring at least half of all private offices, open offices, and computer classrooms to be controll
Wood Tables made for a retail Project
Retail-CI-v4 EQc2:Low emitting materialsposted by Cindy Davis on
My retail project is having cafe tables made by the owners millwork company that would have metal legs and a wood top. If the wood met the requirements of the composite wood VOC (CA
Sidewalk Considered "Bike Network"?
NC-v4 LTc6:Bicycle facilitiesposted by Jenni Betancourt on
Hey LEEDusers - If a sidewalk is min. 5' wide, will GBCI consider that a one-way bicycle network? The project is in a suburb of Chicago. Thanks in advance for comments!
Landscape lighting
CS-v4 SSc6:Light pollution reductionposted by Ricardo Sá on
I am designing the lighting system for 3 major office buildings. Around the building and in some balconies, the architect will specify some green areas and small gardens.
defination occupied spaces vs. ASHRAE 2011 handbook
NC-v4 EQc9:Acoustic performanceposted by Ydo Schuuring on
dear all,
MR c.1 Building Life-Cycle Impact Reduction
NC-v4 MRc1:Building life-cycle impact reductionposted by Shane Geraghty on
Hi, I am working on a new building project which is pursuing LEED certification and excavation filling from a different construction site nearby will be used for the new building. Is excavation
Compliance through furnished measurement
NC-v4 EQc9:Acoustic performanceposted by Martin Stowell on
Is it possible to achieve compliance for this credit by taking reverberation measurements once the multifamily units are occupied and furnished?
Rainfall events to consider under Option 2
NC-v4 SSc4:Rainwater managementposted by Ricardo Sá on
Hi,
Demand response credit requirements vs. best practices under all conditions?
NC-v4 EAc4:Demand responseposted by Joanna Switzer on
In evaluating our Climate Zone 2A / cooling dominated project, it comes as no surprise that 3-7pm in August is the peak occurrence for the (currently) proposed design, with cooling a