NC-v4 MRc1:Building life-cycle impact reductionposted by Mike Workman on
Hi All, Our building we are working on is not existing and will be built new on the site. Do we still qualify for Mrc1 option 4?
Sports Field Exceptions
NC-v4 SSc6:Light pollution reductionposted by Michelle DiPenti on
Has anyone received an exemption for uplight and light trespass for sports fields? Or know the reason why the exemptions from v3 were not carried over?
Locally sourced rebar
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Michelle Rosenberger on
We are struggling to understand the new constraints on locally sourced products and how this new credit encourages any local sourcing at all.
How wide is the definition of coating?
CI-v4 EQc2:Low emitting materialsposted by Rita Paulo on
Hi everyone.
We are checking the project written material of a LEED V.4. BD+C project in Copenhagen.
Documentation
Healthcare-v4 IPp1:Integrated project planning and designposted by Tarik Tadmori on
O.k.
So we just held our workshop for a project.
How is this documented at the design submission stage?
Report of topics covererd and key actions/ownership?
Applying Facility Averages to Commingled Streams
NC-v4 MRc5:Construction and demolition waste managementposted by Ben Austin on
The following are the waste streams that are being collected on the project site:
- Wood
- Metal
Schools: Shop-applied primers
Schools-NC-v4 EQc2:Low emitting materialsposted by Philip Kabza on
Previous restrictions on content of shop-applied primers (such as on structural steel), that were put on hold in v3, appear to not have carried forward at all in v4. Am I correct?
Selling renewable energy
CI-v4 EAc4:Renewable energy productionposted by Borja Sánchez on
Our project has a photovoltaic array that generates electricity which it´s sent totally to the grid, not being consumed directly in the building.
Signed Tenant Lease Agreement
CS-v4 EAc2:Optimize energy performanceposted by Ciaran McCabe on
The LEED Reference Guide states "If a project team wishes to pursue additional credits or thresholds beyond the construction scope of the LEED project, a binding tenant sales and lease agreement mu
Electric Forklifts Innovation Credit??
CS-v4 INc1:Innovationposted by Cora Kenrick on
Hello Fellow LEED Users,
I'm looking for advice.