opaque building envelope construction

NC-v4 EAp2:Minimum energy performance
posted by  Ahmed El-Semary  on 

i need to know what is required to be filled exactly in roof construction and whatis meant by building ID ??

6
Mon Sep 18, 2017, 1:25 pm

Flooring & "categories"

NC-v4 EQc2:Low emitting materials
posted by  Erin Holdenried  on 

Does the flooring category for Option 1 Threshold path include the same materials as LEED v2009 did?  All flooring adhesives, coatings, sealers, grout, etc.?  In Table 5 of the refer

0

Flooring & "categories"

NC-v4 EQc2:Low emitting materials
posted by  Erin Holdenried  on 

Does the flooring category for Option 1 Threshold path include the same materials as LEED v2009 did?  All flooring adhesives, coatings, sealers, grout, etc.?  In Table 5 of the refer

0

underground infiltration structure LID?

CS-v4 SSc4:Rainwater management
posted by  Jens Apel  on 

I am not quite sure if the approach discussed in my project team is a viable way to achieve this credit and would like to check back with you.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Fri Sep 15, 2017, 10:50 am

Visitor parking only

CI-v4 LTc5:Reduced parking footprint
posted by  Karen Elliott  on 

We have an large office space in Central London that has 2 car parking spaces, but the staff will not be able to use them.  They will only be used in exceptional circumstances for visitors.

1
Fri Sep 15, 2017, 9:43 pm

electric bicycles can comply with Green vehicles

NC-v4 LTc8:Green vehicles
posted by  Hanh Truong  on 

Dear all,

My question is that whether electric bicycles can be considered as Green vehicles or not?

0

Cx completion and LEED submissions

CI-v4 EAc1:Enhanced commissioning
posted by  Erin Rowe  on 

Two questions. 1) We are going for all commissioning points on a LEED V4 CI project.

0

Cx completion and LEED submissions

CI-v4 EAc1:Enhanced commissioning
posted by  Erin Rowe  on 

Two questions. 1) We are going for all commissioning points on a LEED V4 CI project.

1
Thu Sep 21, 2017, 6:18 pm

Change to Cx agent

NC-v4 EAp1:Fundamental commissioning and verification
posted by  Cindy Quinn  on 

I'm working on a v4 project currently in CD design phase.

2
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Thu Sep 14, 2017, 1:13 am

Option 2. Third-Party Utility Reporting (1 point)

Homes-v4 EAc5:HVAC Start-Up Credentialing
posted by  Robert Grimard  on 

 

Hi,

I'll soon be the proud owner of a small house in Quebec, Canada and I need clarification on this Option 2 of th Advanced utility tracking. It says:

0