Reduced Truck Idling
Warehouses-NC-v4 LTc8:Green vehiclesposted by Michelle Rosenberger on
Okay first up, I'm confused. The Birds Eye Language above is for the regular New Construction options, not for the Warehouses and Distribution options.
Existing Landscape Area
ND-Plan-v4 GIBc4:Outdoor water use reductionposted by Noriko Nagazumi on
Hi, Our project has a portion of existing landscaped area within the project boundary.
Manufacturer Inventory
NC-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by Jason Grant on
Hi Paula - If an engineered wood flooring manufacturer wanted to qualify a product line under Option 1, is it safe to assume that they would just need to publish the list of chemical ingredients of
Showers & Changing Facilities
CS-v4 LTc6:Bicycle facilitiesposted by Edna Urias on
We were wondering if a Core & Shell building will be subdivided in a future for 2 tenants, do we have to consider shower facilities at 100 feet from each main entrance ?
Zero Lot Line Property
NC-v4 SSc6:Light pollution reductionposted by Edgar Arevalo on
The building that is going for LEED certification is on a zero lot line property.
Discounted Permits as Preferred Parking?
NC-v4 LTc7:Reduced parking footprintposted by Nathan Gauthier on
Have people tried using discounted parking as preferred parking for this credit?
Hiring CxA for Construction other than one hired during Design
NC-v4 EAc1:Enhanced commissioningposted by mohammad Hassan on
Can a different CxA for a project Construction Phase be hired other than the one hired during Design Phase ?
list of approved programs?
NC-v4 MRc4:Building product disclosure and optimization - material ingredientsposted by emily reese moody on
I could have sworn I saw a link somewhere in LEEDUser to a list of approved programs to use for this credit (that also gets updated as USGBC adds more programs), but can't find it now. Did I imagin
BD+C New Construction - New Stadium
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Quentin Jackson on
Hi all, I'm preparing to register a new project (new stadium) and would like to double check that it is a 'single building'.
EPA New Version
NC-v4 SSp1:Construction activity pollution preventionposted by Jennifer Webb on
The EPA has issued the 2017 Construction General Permit (see web page https://www.epa.gov/npdes/stormwater-discharges-construction-activities-2017-cgp) that became effective on February 16, 2017.