Post a question or comment
Credit Filters
Filter by location
Forum
Topic
Replies
Recent

Hybrid recooler

NC-v4 WEc3:Cooling tower water use
posted by  Florian Schmidtchen  on 

Dear all, Our MEP Engineer wants to implement a dual recooling system/the hybrid recooler of the series KAVH.

4
Default Avatar
M.Sc.
LCEE Life Cycle Engineering Experts GmbH
LEEDuser Basic Member
20 thumbs up
Wed Aug 2, 2023, 10:09 pm

CO2 Monitor without Densely Occupied Spaces

NC-v4 EQc1:Enhanced indoor air quality strategies
posted by  Jesse Hunt  on 

Does anyone know if you can achieve a point for CO2 monitors without any densely occupied spaces?

2
Mon Jul 31, 2023, 6:59 pm

Indoor Water Use Reduction - Occupancy clarification

NC-v4 WEp2:Indoor water use reduction
posted by  Subhashkumar A  on 

The project building is a gym building (G+2). On the second floor, it has residential units for its employees. The employees who work in this gym building stay in these residential units.

3
Mon Jul 31, 2023, 1:01 pm

In what case we don't have to run a baseline model with all 4 rotation

NC-v4 EAp2:Minimum energy performance
posted by  Rajat Wadhwa  on 

Hi , I am working on a LEED Data center model with majority of space as vault, now I know for an existing building we dont need to rotate but for a data center do we need to rotate as the majority

1
Mon Jul 31, 2023, 1:05 pm

Default EIA rates for India

NC-v4 EAp2:Minimum energy performance
posted by  Moses Chong  on 

Hi! I'm working on a project in India. We cant obtain the utilities rates so we were trying to use the deafault EIA rates like other projects we did in the US.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4460 thumbs up
Fri Jul 28, 2023, 3:14 pm

Pilot Credit SSpc129: Composting Offsite

NC-v4 INc1:Innovation
posted by  Juan Carlos Valenzuela   on 

Hi Leed Users, 

We are working on a project with offsite composting planning as well as receptacles for organic waste, however, we have the following questions: 

0

Off street parking and on street parking

NC-v4 LTc7:Reduced parking footprint
posted by  Azaz Ansari  on 

Gentlemen,

1. Could you please explain the following statement:

    "Preferred parking is not required if no offstreet parking is provided".

7
www.afogreenbuild.com
Green Building Consultant
LEEDuser Premium Member
250 thumbs up
Thu Jul 27, 2023, 6:42 am

2-year Establishment Period

NC-v4 WEp1:Outdoor water use reduction
posted by  Kun liu  on 

We are working on a project in South Holland, IL.

2
Sustainability Director, Certifications & Compliance
Jacobs
LEEDuser Expert
469 thumbs up
Thu Jul 27, 2023, 6:23 am