NC-2009 PIf1:Minimum Program Requirementsposted by Jodie Clarke on
I have a project that registered using LEED-CS v2.0 in 2007.
Structures connected through a walkway
NC-2009 PIf1:Minimum Program Requirementsposted by Ricardo Sá on
I'm working on a project that has two structures connected through a suspended walkway. The first consists mainly of warehouse areas (distribution centre) with some auxilliary office areas.
Certify a Building Extension
NC-2009 PIf1:Minimum Program Requirementsposted by Anna Ohlmeier on
Hello all, we would like to certify the extension of an already LEED certified building. Do anyone know if there are other regulations or it is possible to extend the first certification?
Exclude retail?
NC-2009 PIf1:Minimum Program Requirementsposted by Mike D on
Our project has got some retail on the ground floor of an office building that the design team does not want to include in the LEED assessment.
Where is the Special Circumstances Option?
NC-2009 PIf1:Minimum Program Requirementsposted by NA AN on
I got the Agent form signed by the legal department and need to upload to leedonline. They told me to upload under Plf1 using the speical circumstances option.
LEED CI - Scope of work required
NC-2009 PIf1:Minimum Program Requirementsposted by Michael Smithing on
Is there any requirement in the LEED CI MPRs (which I have not found) that a tenant space actually undergo modification to be certified?
Must Use a Reasonable Site Boundary
NC-2009 PIf1:Minimum Program Requirementsposted by Becky Dix on
The project in question is being constructed on an urban medical campus.
Using interpretation 10203 for a hotel site
NC-2009 PIf1:Minimum Program Requirementsposted by Susan Di Giulio on
We have a LEED-NC 2009 hotel project and are trying to determine if we conform to interpretation ID#10203 of 07/01/2012 allowing certain hotel, school and other multiple-building projects to regist
Multiple Buildings Project Certification
NC-2009 PIf1:Minimum Program Requirementsposted by Mario S. on
We have a project with 3 buildings located on the same plot, that are physically attached by two underground levels made up of technical rooms, parking spaces, bicycle racks, showers and garbage ro
LEED NC 2009 Group Certification
NC-2009 PIf1:Minimum Program Requirementsposted by Neumann Monson on
Our project consists of two buildings on a shared site, to be built in two phases.