NC-2009 EAp2:Minimum Energy Performanceposted by Graham Langton on
Regarding what is taken as a process energy.
Baseline Garage Ventilation
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Greetings, ASHRAE 62.1-2007 establishes a ventilation exhaust rate for garages of 0.7 cfm/sq.ft. Our project has lower rate and besides it applies a CO control settings of 20mg/m3. The question is:
Big Ceiling Fan
NC-2009 EAp2:Minimum Energy Performanceposted by Laura Long on
I have a job where there are several Big Ass Fans. My problem is in determining how to model them in the energy simulation.
District Thermal Energy and Single LEED project boundary
NC-2009 EAp2:Minimum Energy Performanceposted by MARCIO OROFINO on
The project comprises four hospital buildings, called B, C, D and E, and each building is registered as an individual project on a campus basis.
backup energy source
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
Hello. I’m dealing with the calculation method for the credits relative to EA section. I don’t understand the meaning of the following sentence of paragraph G2.4 of ANSI/ASHRAE/IESNA STANDARD
SEER of split AC unit
NC-2009 EAp2:Minimum Energy Performanceposted by Jatuwat Varodompun on
In Thailand, there is no SEER testing as indicated for a small air conditioners in table 6.8.1A of ASHRAE 90.1 standard. Only EER is normally required to be tested here.
Table EAp2-5
NC-2009 EAp2:Minimum Energy Performanceposted by Isabel Santos on
Dear all, I am having one difficulty in filling the form of EAp2.
Exterior Lighting not yet designed
NC-2009 EAp2:Minimum Energy Performanceposted by Maya Karkour on
Dear All, I am modeling a project which still has no exterior lighting design (the owner will decide on this when the building is almost complete). In the preliminary design review, I put the val