Baseline Pumping Power
NC-2009 EAp2:Minimum Energy Performanceposted by Ahmed Labeeb on
Based on ASHRAE 90.1, the chilled water pumping power must be 22 W/gpm and does not mentioned the effect of pumping head.
Selecting baseline for mixed use building
NC-2009 EAp2:Minimum Energy Performanceposted by Lavanya Veerappa on
We are working on a project which is mixed use facility (6 storey/G+5) . The first & 2nd floor is used for office & remaining for residential.
Heating only system; Baseline modeling of DHW
NC-2009 EAp2:Minimum Energy Performanceposted by Vassil Vassilev on
Markus, thanks a lot for your answer. Another issue appeared to this Heating only system - Baseline modeling of DHW (Domestic Hot Water). The Proposed model is having a gas fired boiler to provide
mandatory efficiency for backup system
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
Shall the mandatory efficiency of section 6.4 (Tables 6.8.1) be verified also for a chiller that works as backup system (the chilled water is provided in normal conditions by district cooling)? Be
Energy modeling - ASHRAE §G3.1.2.4
NC-2009 EAp2:Minimum Energy Performanceposted by Julien Daclin on
Hi all, We are undertaking the energy modeling of an office building and the Baseline is using a System 7, climatic zone is 4a.
ASHRAE 90.1 Mandatory provision (Labeling)
NC-2009 EAp2:Minimum Energy Performanceposted by Manuel Martin Delgado on
Hello, I am working on a project outside US and I am wondering how to approach the mandatory provision below. 6.4.1.5.1 Mechanical Equipment.
Peak Demand...hourly, daily, weekly, monthly
NC-2009 EAp2:Minimum Energy Performanceposted by Jean Marais on
Common sense tells me they are not interested in by the second peak energy demands for each end user...so to ask the stupid question: Which average value should I output here...hourly average annua
Data Center Energy Performance Calculator
NC-2009 EAp2:Minimum Energy Performanceposted by Wei Jiang on
Dear all, We are trying to calculate the IT & electricial energy consumption of a data center, using the Minimum Energy Performance Data Center Calculator.
IES ApacheHVAC - Proposed system for VRF
NC-2009 EAp2:Minimum Energy Performanceposted by Alice chen on
Hi All, I am modelling a VRF system using ApacheHVAC in IES. But have no idea which prototype to choose.
ACP and EAP2?
NC-2009 EAp2:Minimum Energy Performanceposted by Tatjana Ernst on
Hello Everyone, we are certifing a new construction building in Germany. We have a question regarding the use of ACP and EAP2.