Baseline HVAC DCV Sequence

NC-2009 EAp2:Minimum Energy Performance
posted by  Cory Duggin  on 

When the baseline system is required to have DCV, how should it be controlled. I'm not aware of any sections that details how the controls should work when it is implemented for the baseline.

1
Fri Dec 11, 2015, 3:39 pm

Ventilation and Energy Efficiency

NC-2009 EAp2:Minimum Energy Performance
posted by  Keerthi Ratnayake  on 

Hi, We are designing a building for tropical climate condition and thinking of having natural ventilation and mechanical ventilation only. i.e.

1
Tue Sep 17, 2013, 1:31 pm

Baseline for Ventilation Fan unconditioned space?

NC-2009 EAp2:Minimum Energy Performance
posted by  Zonda E. Team  on 

What is the baseline for a ventilation fan providing outdoor air to an unconditioned space?

1
Wed Jun 11, 2014, 1:01 pm

How to include Parking Ramp Energy Use in Small Bldg?

NC-2009 EAp2:Minimum Energy Performance
posted by  Kevin Flynn  on 

I have just begun working on a project that features a small (under 20,000sf) office building on a large public plaza on top of a below grade parking ramp.

0

Energy Update ballot

NC-2009 EAp2:Minimum Energy Performance
posted by  Kathryn West  on 

when will the results of the ballot be posted?

0

Unitary Cooling Efficiencies

NC-2009 EAp2:Minimum Energy Performance
posted by  TOMAS URIBE  on 

Hello, We are simulating a type 4 system in our baseline and need to know if the efficiency ratings specified in table 6.8.1B (and tables 6.8.1.A, 6.8.1D) do include supply fan power and hence ne

1
Tue Jul 10, 2012, 1:34 pm

Change form

NC-2009 EAp2:Minimum Energy Performance
posted by  Nicolas Martinez Ochoa  on 

Hi, I am working in an office building. I have completed the “minimum energy performance v2009” spreadsheet, but the project uses the v05 form. Is it possible to change the form to a newer form?

1
Tue Nov 8, 2016, 10:53 pm

Zone isolation

NC-2009 EAp2:Minimum Energy Performance
posted by  Ricardo Sá  on 

In an office building, shall meeting rooms (sporadically occupied within the schedule defined for the remaining occupied office areas) be considered an isolation zone according to ASHRAE 90.1 (2007

1
Tue Oct 22, 2013, 8:09 pm

Energy Model Baseline for a Dome

NC-2009 EAp2:Minimum Energy Performance
posted by  Nelina Loiselle  on 

We have a data center project where the owner decided to design-build a dome structure because of the efficiencies inherent in this type of construction.

1
Mon Sep 19, 2011, 5:20 pm

Denial of EA PR2

NC-2009 EAp2:Minimum Energy Performance
posted by  Roxanne Button  on 

A client has asked for my advice in appealing the denial of PR2. I've taken a quick look at the review comments but will be digging deeper into it in the next couple of days.

1
Fri Mar 25, 2016, 2:35 pm