metal wall louvers
NC-2009 EAp2:Minimum Energy Performanceposted by Francesco Passerini on
In the building that I’m modeling there are metal wall louvers. Some of them are connected to ductwork (for ventilation), some of them ventilate directly technical rooms.
ASHRAE Mandatory Provisions for Power
NC-2009 EAp2:Minimum Energy Performanceposted by Carolina Vergnano on
I'm working on LEED for a stadium, and we have a bit of trouble interpreting requirements of ASHRAE 90.1 -2007 section 8. The project will have a tranformer that will filter the high voltage.
Modeling semi heated space with mechanical ventilation
NC-2009 EAp2:Minimum Energy Performanceposted by Ashwin Kumar on
We are working on the energy modeling for Industrial Manufacturing facility in which some places can be classified as “Semi heated spaces” as per ASHRAE 90.1 2007 definition.
Baseline Fan Power: Systems 6 and 8 ASHRAE 90.1-2007 Appendix G
NC-2009 EAp2:Minimum Energy Performanceposted by TOMAS URIBE on
If our Baseline building design HVAC system is ASHRAE’s #6 or #8 (according to TABLE G3.1.1B).
I am relatively new to LEED
NC-2009 EAp2:Minimum Energy Performanceposted by le sang on
I am relatively new to LEED and I would like to know if there are systems out there and gain many credits for a new office HQ in IrelandThe other question is related with how to prove a process loa
Delineation of systems AND heat sources
NC-2009 EAp2:Minimum Energy Performanceposted by Wes Lawson on
Table G3.1.1A states that buildings that are “…eligible for more than one baseline system type should use the predominant condition to determine the system type for the entire building except as no
ASHRAE 90.1- LIGHTING POWER DENSITY SOFTWARE.
NC-2009 EAp2:Minimum Energy Performanceposted by Ghaleb El Mheirat on
We are currenlty in the design process of a building targetting to be LEED certified under version 3.0.
Which system
NC-2009 EAp2:Minimum Energy Performanceposted by David Anderson on
I have a project I am trying to model. the overall building is just over 25,000sf. The is an office area that is about 11,000sf and enclosed parking area, and an enclosed utility space.
District Cooling system and energy modeling(visualDOE)
NC-2009 EAp2:Minimum Energy Performanceposted by Mohamed Ravuthar, LEED AP, BD+C on
How to handle District Cooling system into energy modeling(visualDOE). 1.Is it required to do energy modeling for District Cooling system for LEED?