Commissioning of plumbing fixtures when no hot water
NC-2009 EAc3:Enhanced Commissioningposted by Emmanuel Pauwels on
The review comments of the basic Commissioning of our project says the following " it appears that all systems included within the LEED-NC project scope of work have not been included.
Testing Adjusting & Balancing (TAB)
NC-2009 EAc3:Enhanced Commissioningposted by Michael Murphy on
Are there any LEED specific requirements for TAB work?
Commissioning Manual and Report
NC-2009 EAc3:Enhanced Commissioningposted by Jalal Avades on
Our project commissioning exercise filled more than 30 binders and if we scan them and upload them it will be couple of Giga Bytes of files.
smoke leakage test for duct
NC-2009 EAc3:Enhanced Commissioningposted by Abdulla Anwar on
Our MEP sub-contractor need to clarify if we can use an smoke capsule for duct leakage test? prior to air leakage test since the project specs is giving a small allowable 1% from basis of design?
Signed Contract with the CxA
NC-2009 EAc3:Enhanced Commissioningposted by Mohamed M. Abd Elhameed on
We are pursuing LEED Certification for a 476921.20 sq ft Mixed Use Office Building in Egypt.
Major Change to Who Can Be a CxA!
NC-2009 EAc3:Enhanced Commissioningposted by Scott Bowman on
I was trying to do some catching up, and the July Addenda has a very significant change to who can be the CxA.
EAc3 - Enhanced Commissioning, LEED v2009
NC-2009 EAc3:Enhanced Commissioningposted by Jared Reed on
Our project is pursuing EAc3 - Enhanced Commissioning. The reference manual states that the CxA performing the enhanced commissioning must also perform the fundamental commissioning.
How to apply the enhanced commissioning task to existing?
NC-2009 EAc3:Enhanced Commissioningposted by Dave Hubka on
Hi Scott, We are involved with a major addition to an existing building. We will be certifying the entire building.
District Energy System owned by Government vs. Owner
NC-2009 EAc3:Enhanced Commissioningposted by Erin Holdenried on
My question is in regard to both EAc3: Enhanced Commissioning and EAc5: Measurement and Verification credits in relation to a District Energy System.
Timing of systems manuals
NC-2009 EAc3:Enhanced Commissioningposted by Melinda Shah on
The LEED NC multiple building project we are working on has been occupied for 6-18 months (depending on the building) and we have everything ready to submit everything for the construction review e