flush out possible by phase
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Sahar Abi-Ziki on
Hello the first phase (parking garage) of our project will be delivered to client for occupancy now, but the rest of the project will still be under construction for a while.
Defined Flush out Area
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Thomas Boyd on
Hello everyone - Our project's registration details reference building square footage as 51,441. However, we've only finished 40,100 sqft.
Combination of Test and Flush
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Michael McVinney on
On a hangar project, there is a conditioned Admin space and an unconditioned Hangar space.
four IEQc3.2 questions....
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Carrie Laurendine on
1) ive looked at space matrix (this is a library project)... from what i gather EVERY space has to count.. even spaces not regularly occupied (mech closet, janitor closet, etc).
Flush-Out Requirement for a Naturally Ventilated Building
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Eric Carbonnier on
The project is an 8 story residence hall on a university campus. The building is not equipped with a central ventilation system and dorm rooms rely on natural ventilation.
majority residential
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Courtney Royal on
Our project is a multifamily building with several common spaces on the cellar, main level, and top level of the building. However, majority of the building is apartment units.
Credit 3.2, Option 1, Path 2
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Douglas Blakeslee on
We are the GC for a new small (4,000 SF) Leed Certified fast food restaurant with 3,800 CFM of outside air when occupied. We plan to do our initial 3,500 CF/SF flushout over a weekend.
Flush out in tropical climate region (Climate Zone 1)
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Adi Negara, LEED AP BD+C on
Hello, Our project is in Indonesia (Climate Zone 1), which happened have high humidity (70-85%) all year long. Our building design only incorporate natural ventilation and AC (VRF system).
Concerning Carpet
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Omar Elrawy on
Dear all, We have a project where we intend to pursue Option 1 Path 1, We will install furniture after completing the flush-out, but the architect is concerned about the carpet install