IAQ Flush out-using temporary exhaust systems
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Stella Stella on
Hi, We are proposing a IAQ flush out procedure for our facility which consist of a lot of FCU’s. Due to the FCU’s the flush out procedure is excessively long.
IAQ Testing using screening tool.
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Marcia Weekes on
Has anyone had experience with meeting the IAQ testing requirements using the Directsense IAQ Plus Screening tool from Graywolf Sensing Solutions.
Implementing IAQ testing shell space
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Summer Minchew on
Noting that an equivalent to IEQc3.2 is not available within the LEED-CS rating system, is it safe to assume that future tenant space(s) within a LEED-NC project would not be subject to IAQ testing
Air testing related to partial renovation per floor
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Julie Barth on
I have a client who is asking about air testing for an office building renovation project where small parts of each floor will be renovated.
Number of air testing samples
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Qian Tang on
Our project office building has 22 floors and is divided in 4 portions – north wing, south wing, east wing and west wing.
Questions.
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by ethen mcmanus on
Listed below is my list of questions: A) We have several FRESH air handling units and REGULAR air handling units on the roof of our building.
Combine options
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Leandro Silva on
We are certifying a Project and we are preparing the documentation for the EQ credit 3.2 Construction Indoor Air Quality Management Plan – Before Occupancy.
Maximum Temperature
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Omar Elrawy on
Dear All, I need to ensure that in the 60/60 rule, I do not find anything about the maximum indoor temperature during flush-out, please advice if I can maintain any indoor temperature as long as it
Purpose behind the 60% RH parameter?
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Landry Watson on
The reference guide is clear that 14,000 CFM of OA per SF (that is >60deg and
Path 2 Flushout
NC-2009 IEQc3.2:Construction IAQ Management Plan—Before Occupancyposted by Amy Harmon on
Our project went with Path 2 Post-occupancy flush out. All AHUs required 2-4 days of flush out before occupancy could occur and about 24 days post occupancy.