Shading of Hardscapes
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by JOHN COOK on
We want to show that we are shading our hardscape but performing the necessary modeling of vegetation shadows at 10am, 12noon and 3pm on the summer solstice is proving difficult.
No car park or external areas
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by Maya Karkour on
Hello, The project we are working on does not have any parking lots or Non roof hardscape surfaces (building footprint occupies all the site). Is this credit still achievable ?
Unpaved Parking
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by Michael Smithing on
The reference guide indicates that parking should be included in the hardscape area - this is good because much of the parking at our project uses an open grid paving system.
Parking under building - still need SRI ?
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by Jaida Anderson-Lozano on
My project is currently assessing which credits for EBOMv2009 can be achievable by reviewing the LEEDonline forms. For credit SSc7.1 the project will achieve compliance via Option 2.
parking lot shaded by low-SRI building
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by Chris Miller on
The parking lot is shaded by the building for much of the measured time, but the building is not "an architectural device(s) or structure(s) that have a SRI of at least 29".
Parking garage... outside project boundary
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by CY Ng on
A separated 6-storey parking garage under the same management of our project building located next to our project site.