Can the existing roof count?
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Kelly Wieczorek on
If our existing roof meets the requirements can we achieve the credit, or does there have to be a change/upgrade from the existing to comply?
Material SRI
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Mohamed Hesham on
i'm participating in a LEED ebom project where the construction was completed in 1990 , the roof tiles are white terrazzo tiles but we can't get any data or documentation from the manufacturer , is
Green Roof Installation After PC for C&S
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Patrice McVeigh on
Hi, I have a Core & Shell Project that will be installing a Green Roof after the Post Construction stage (i.e.
Roof Area definition
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by David Tompos on
The definition for roof area indicates that only the roof area directly above the Gross Square Footage should be used for the Option 1 - 75% calculation.
Partially certifying building
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by h r on
Upper floors of building are utilized as hotel and lower floors are utilized as office. Owners are diffrent. Only the office is going to certified under LEED EB except hotel.
Floated tile paving and Heat Island Effect
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Mauricio Ramirez on
I have a building that has in the most part of their roof, a floating tile paving, that creates an air-chamber between the slab of the roof and the tilies of the paving.
Roof area covered 90% by equipment
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Ran Zhang on
Hi, I am working on a 10 floors office project building in Japan. For roof area, there are only about 100 sqm exposed surface (less than 10% of total area).
LEED Certification: EBOMv2009 SSc7.2 Heat Island Reduction Roof
EBOM-2009 SSc7.2:Heat Island Reduction—Roofposted by Andres Giraldo on
Our goal was to submit for certification tomorrow February 13, 2015.