Submetering requeriments for exclusive chiller for tenant space
CI-2009 EAc3:Measurement and Verificationposted by Maria Isabel Conde on
The project is located within a building, its area is less than 75% of the total area of the building. The project has a chiller plant that only supplies the project area.
To meter or not to meter
CI-2009 EAc3:Measurement and Verificationposted by Rudolph Carneiro on
I have a store (case 1) with a small 60 ton chiller, 2 AHU's, lighting, and plug loads. If HVAC, plug loads, and lighting can be measured on one meter, how many meters do I need?
BTU Metering for Existing HVAC
CI-2009 EAc3:Measurement and Verificationposted by Jareb Ketay on
I have a tenant renovation project occupying 1 story of an existing 10 story building (
Case 1 Option 2
CI-2009 EAc3:Measurement and Verificationposted by breeze glazer on
We have a situation where the tenant space, is within a building owned, by the owner.
case 1, however what happens if space will be owned
CI-2009 EAc3:Measurement and Verificationposted by Courtney Royal on
for example, the project is a large building with a commercial spaces on each floor that will be sold.
M&V case 2
CI-2009 EAc3:Measurement and Verificationposted by Chris Miller on
CI project, 75% or more of the space is occupied by the tenant, and I have seen the 4/1/12 addenda with the replacement language for Case 2.
Alternative Compliance Path Case 1: Lease Document
CI-2009 EAc3:Measurement and Verificationposted by Carolina Acevedo on
Is there an alternative compliance approach to this credit? My project falls under Case 1 (less than 75% of the project space), but my client owns the floors hence the lack of a lease agreement.
Spot Metering for CI 2009 EAc3 Option B
CI-2009 EAc3:Measurement and Verificationposted by Michael Hill on
I am working on a project which is considering pursuing CI 2009 EAc3 Option B. I am wondering if continuous metering is required for this path or if spot metering would be acceptable.
LEED-CI EAc3
CI-2009 EAc3:Measurement and Verificationposted by Tapio Peltonen on
LEED-CI 2009 EAc3 Case 1 Online form has options for sub-metering or central plant. Does the central plant mean that the tenant space is served by e.g.