Will RECs from TIGR fulfill the credit requirement for EAc4 LEED CI v2009 ?
CI-2009 EAc4:Green Powerposted by Rowena Rawte on
For a project in Singapore the client are planning on purchasing Green RECs from TIGR.
The owner buys the energy
CI-2009 EAc4:Green Powerposted by Mathilda Jonsson on
Hi all In my LEED CI project the tenant are sub metering their energy usage and are then paying the building the owner for the amount of energy used.
Green Power - Carbon Offset
CI-2009 EAc4:Green Powerposted by Henry Mak on
Hi All, I am working on a project located in China.The owner is the local electric company who has solar power and wind power supply.
LEED EB / CI RECS-is sharing double-counting or tenant advantage
CI-2009 EAc4:Green Powerposted by Kathy Collins, LEED AP , WELL AP, CxA BE Cx on
We have an EBOM property that was certified with 100% RECs in 2009, and we've been maintaining the purchases of RECs for recert in 2014.
green power - purchased percentage
CI-2009 EAc4:Green Powerposted by Andy Plogsted on
Our client owns the building and occupies 50% of the square footage of a singularly metered building. The owner (our client) signed a contract to purchase green power for 30% of the total building
100% Green energy supply contract
CI-2009 EAc4:Green Powerposted by Esther Izquierdo on
Hi, After reading all comments I'm still not clear about the following, I hope you can help me: - We have not gone through the building simulation route in EAC1.3, so in principle we would need to
REC vendors for Singapore Project
CI-2009 EAc4:Green Powerposted by Yong Lee Low on
For our Singapore projects, we need to buy REC but are not sure where to start searching?
Two Year HVAC Electricity Use
CI-2009 EAc4:Green Powerposted by Joseph Greene on
Our LEED project occupies 30% of the total building floor area. The energy model modeled the entire building due to a central boiler and condenser water plant.
Green Power for LEED-CI Retail
CI-2009 EAc4:Green Powerposted by Linda Davisson on
Can anyone confirm that Green Power is 2 points for LEED-CI Retail instead of 5 points for LEED-CI?
Can the project team purchase the RECs?
CI-2009 EAc4:Green Powerposted by Crista Shopis on
The reference guide states that "the tenant AND project team can purchase Green-e accredited RECs".