Suggestions for Calculating Casegood area

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  James Shook  on 

We have a library project that is reusing metal shelving. Since it is being used for the same purpose this credit indicates it should be part of MR1.2.

1
Tue Mar 29, 2011, 1:53 pm

Exterior and Party Walls

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Shirong Meng  on 

The elements of "Exterior and Party Walls" include shell or not? It seems to be exterior walls seperated from outdoor and party walls seperated from other spaces.

1
Mon Nov 21, 2011, 6:28 am

furniture in building reuse

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Yaser Al Sharif  on 

1.please can any one help me how to calculate the Office Systems Furniture? it is not clear for me ... we have retained all offices furniture and we didn't buy any thing new

3
Sustainable Building Consultant
Green Bridge Consulting
LEEDuser Expert
28 thumbs up
Tue Jun 2, 2015, 5:30 pm
7
Wed Apr 1, 2015, 6:36 pm

Full height glass partitions

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Charles Nepps  on 

Would full height glass partitions be calculated both sides as a partition wall, or one side as glazing?

3
NH Green Consulting
LEEDuser Premium Member
80 thumbs up
Fri Apr 25, 2014, 4:45 pm

We are working on food

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Elizabeth Powers  on 

We are working on food production facility and offices. The offices will be in the first two floors of an historic building that the developer is renovating as part of the project.

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Fri Apr 25, 2014, 3:45 pm

Definitions

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Mike D  on 

The table lists 3 components: - Prior condition area - Completed design area - Retained components area I understand the prior condition area which is the existing components before any works.

4
Sustainable Building Consultant
Green Bridge Consulting
LEEDuser Expert
28 thumbs up
Tue Mar 26, 2013, 4:36 pm

Maintaining just

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Mike D  on 

Can we tabulate just one component e.g. finished ceiling - and not list all other components in the table?

3
Default Avatar
LEEDuser Basic Member
45 thumbs up
Mon Mar 25, 2013, 5:50 pm

Existing Finish

CI-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elements
posted by  Sara Neff  on 

I looked through the reference guide for a definition of 'finished,' but I couldn't find one, so I'm hoping someone here can help: I have a CI project that is moving into a space that has existing

2
Founder & Community Director
Metricorps
LEEDuser Expert
7780 thumbs up
Sun Sep 25, 2011, 10:05 am