EBOM IEQp1: Dedicated OA to classroom FCU's

EBOM-2009 IEQp1:Minimum IAQ Performance
posted by  James Doyle  on 

For EBOM IEQp1 we have a school using a dedicated ventilation AHU providing ventilation air to classroom FCU's.

1
Thu Nov 24, 2011, 12:18 am

Cooling Tower for Back-up Diesel Generators (DG)

EBOM-2009 WEc4:Cooling Tower Water Management
posted by  Anshul Chawla  on 

The project site has 3 cooling towers of 215 ton capacity each. These cooling towers serve the HVAC system of the building and are operational for 8-10 hrs on all working days.

1
Tue Dec 20, 2011, 4:46 pm

VRP Compliance Calculator

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Juliana Malho  on 

We have a CI project with multiple zone units and VAV system. We are using template VRP compliance calculator.

1
Mon Dec 19, 2011, 2:48 pm

Technical Rooms

CI-2009 IEQp1:Minimum IAQ Performance
posted by  Juliana Malho  on 

Does technical rooms, as IDFs rooms needs to have outside air renovation?

1
Fri Aug 31, 2012, 5:55 pm

Advice on acceptable approach to credit achievement for IEQc5

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Shelley Duan   on 

Is a covered exterior grate system (e.g, outside a vestibule) at all high volume entryways an acceptable approach to credit achievement for IEQc5? Any advice or guidance would be most appreciated.

1
Fri Nov 25, 2011, 8:18 am

Requirements

CS-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Products
posted by  Guillermo Hernandez Espinoza  on 

This may seem to be a silly question, but is causing me lots of issues, is there any kind of requirement to achieve this credit other than just an all or nothing?

1
Fri Nov 25, 2011, 5:02 am

Target Finder

NC-2009 EAp2:Minimum Energy Performance
posted by  TEY SIUNG  on 

We are building a Hotel in Doha, Qatar. We are try to apply for LEED certified. While I start , I meet a Target Finder problem. This Target Finder only design for US climate.

1
Mon Nov 28, 2011, 4:48 pm

EAp2 - Compliance to ASHRAE standards

CI-2009 EAp2:Minimum Energy Performance
posted by  Paolo Losi  on 

Hi all, we are willing to pursue LEED CI certification for our office in Italy.

1
Mon Nov 28, 2011, 5:42 pm

Definition of hard-lid ceiling?

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Renee Shirey  on 

I have a situation where I cannot eliminate a sloped acoustic ceiling with a gyp ceiling, and the walls do not go up to the deck (they go to the underside of trusses).

1
Mon Nov 28, 2011, 11:43 pm

Base building EBOM credits denied

CI-2009 IDc1:Innovation in Design
posted by  Raphael Sperry   on 

I've had a pair of CIv2009 projects just denied (at first review) a couple of innovation points where the base building provides Green Cleaning, Integrated Pest Management, and a Zero-Waste Plan to

1
Sun Dec 18, 2011, 4:50 am