Forum quick links
Existing Imperviouness
CS-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Markus Henning on
My question is. The Guide says choose Case 1 Sites with Existing Imperviousness 50%or less or Case 2 Sites with Existing Imperviousness greater than 50%.
Baseline Exhaust Fans vs. Proposed ERV
NC-2009 EAp2:Minimum Energy Performanceposted by Candice Rogers on
I am modeling a building that directs all building exhaust through an energy recovery ventilator, including bathroom exhaust.
ARI Certification for VRF equipment in LEED-NC 2009
NC-2009 EAp2:Minimum Energy Performanceposted by Mauricio Ramirez on
Talking about a VRF HVAC system. Is it a mandatory requirement that the VRF condenser and evaporative units must be ARI Certified, according with the Standard 90.1-2007?
external lighting LPD contribution to percentage energy savings
CS-2009 EAc1:Optimize Energy Performanceposted by Puteri Shireen Jahnkassim on
Hello there What does this mean : Ensure that no credit is taken in the proposed case for lighting reduction on tradable surfaces" Does this mean if the LPD for facade lighting for a designed b
LPD for space with higher headroom
NC-2009 EAc1:Optimize Energy Performanceposted by William Wong on
Does anyone know what headroom height are based on when ASHRAE design the LPD for space-by-space method (Table 9.6.1) ?
Occupancy Fitness Center
CS-2009 WEp1:Water Use Reductionposted by Ralf Lehmann on
Has anyone of experience in including a fitness center m to an office building. One of the tenants of our Project will be a fittness center. All fit outs will be done by the tenants.
Non-fibrated aluminum paint
NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatingsposted by Bruce Maine on
This is actually a LEED for Healthcare question dealing with exterior applied products. In several roofing sections we ask for "non-fibrated aluminum paint".
Office Space With 25% Data Center Changing to 100% Office-June
EBOM-2009 EAp2:Minimum Energy Efficiency Performanceposted by Michelle Bracewell-Musson on
There are four buildings that are leased by the State and one of the buildings currently has 25% if it as a Data Center.
Recycling Areas Designation
NC-2009 MRp1:Storage and Collection of Recyclablesposted by Sunayana Jain on
In the floor plan, is it required to document the recycling areas as paper, corrugated cardboard, glass, plastics and metals specifically or just designating as recycled areas in floor plan will be
Entering "total project space equipment capacity" - LEED form
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Seema Pandya on
In the LEED Online form for option 1 section 1.4: Mechanical System Design Criteria, there is a place for you to enter the total space loads for heating and cooling and another entry that asks for