Temporary construction material left on-site.
NC-2009 MRc2:Construction Waste Managementposted by Keith Robertson on
Should MRc2 include temporary construction materials that are left on-site. In particular, it is common for a crane-base, or temporary concrete dead-men or casting beds to be left on-site.
Areas to be considered
CS-2009 IEQp1:Minimum IAQ Performanceposted by Angela Saggin on
Hi! What areas/rooms should we consider inside an appartment for the calculation of naturally ventilated spaces?
Sauna
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Jim Park on
I am working on a hotel project, which would use standard fixtures (no high-efficiency fixtures), but would still earn 2 points under WEc2, and 2 points under WEc3 due to utilizing recycled gray wa
LEED NC - Tenant Commissioning
CS-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Jennifer Preston on
Our base building will be fully commissioning, but the small first floor tenant fit out is not in the scope of the project, beyond providing base building systems.
Option 1 and Option 2 Combined?
EBOM-2009 SSc7.1:Heat Island Reduction—Nonroofposted by Jason McIntyre on
I have a project that has a detached parking garage, of which has spaces on the top level (uncovered). I also have surface parking spaces on the site...
EAp1 Review Comments
EBOM-2009 EAp1:Energy Efficiency Best Management Practicesposted by matthew strong on
We recently received review comments asking us to list energy demand savings and maintenance cost savings for our EEMs.
Upgrading Older Models
CI-2009 EAc1.4:Optimize Energy Performance—Equipment and Appliancesposted by Curt Pascoe on
Has anyone completed the credit template in LOv3 recently? The form no longer refers to "upgrades" per the LEEDuser calculator or the Reference Guide Calculations.
I also agree the HTA index
Pilot-Credits PC29:Housing and Jobs Proximityposted by Evelyn Smith on
I also agree the HTA index was extremely user friendly. Our LEED for Homes project was easily able to use this credit as we are located in Washington, D.C. and centrally located near jobs.
Baseline HVAC Selection
NC-2009 EAp2:Minimum Energy Performanceposted by April Rice on
We have a 5 story non-residential building (located on a campus), with a mechanical penthouse (with roof) above.
Walk-off at Loading Docks?
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Heather Schafer on
I am working on 2 University projects, both seeking LEED certification. Both buildings have loading docks with a back-of-house entry.