Water consumption calculation - showerhead flow rate pressure
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by GPS Development on
I'm working on a LEED project in Asia. The water pressure for shower here is set at 3.5 bar (~50 psi). However, the baseline used by LEED is 2.5gpm at 80 psi.
Modeling DCV in open space offices
CS-2009 EAp2:Minimum Energy Performanceposted by Lucie Cervena on
x
Modeling DCV in open space offices
CS-2009 EAp2:Minimum Energy Performanceposted by Lucie Cervena on
I am in the process of simulating 7 floor office building. Five of these floors are designed as open space offices, the others are designed as small offices.
wood
CI-2009 MRc2:Construction Waste Managementposted by Juliana Malho on
Whern you burn a wood that was diverted from landfills, is it considered recycling??
Laminating Adhesive proof of no UF
NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Productsposted by Laura Charlier on
We submitted an MSDS as proof of no urea-formaldehyde in a laminating adhesive and got this response from the reviewer: An MSDS that does not list urea-fomaldehyde is not confirmation that the pro
This classification confuses to me
Pilot-Credits EApc67:Energy Jumpstartposted by Bill Swanson on
I'm not understanding why this is a Pilot Credit. Per USGBC's website. "What is the Pilot Credit Library and its purpose? a.
Eggshell
NC-2009 MRc6:Rapidly Renewable Materialsposted by Fernanda Cortes on
If a paint contains in its composition grams of mashed eggshell, is this component considered a rapidly renewable content ?
Architect Signatory
NC-2009 EAp2:Minimum Energy Performanceposted by Christopher Getz on
Does the Architect Signatory have to be a LEED AP? or just a registered Architect?
AHU measurements
EBOM-2009 IEQp1:Minimum IAQ Performanceposted by Luis Parada on
In our building we have two main AHU that supply 26 AHU (one for each floor of the building) and then we have VAVs for each zone in each floor. Do I need to perform measurements just in the two ma
'Leaks in Return Ducts and Air Handlers..be checked..repaired'
EBOM-2009 IEQc1.5:IAQ Best Management Practices—Facility Alterations and Additionsposted by Michelle Bracewell-Musson on
The Contractor will not be using the HVAC during a minor alteration and there is no HVAC scope except for Air balancing and cleaning of ductwork. How much sealing is required?