Partial Floor LEED Certification

CI-v4 MPR3:Must comply with project size requirements
posted by  Edgar Arevalo  on 

I have a project that is a partial floor fit-out where the client would like that partial space to be LEED certified.  The project space is approximately 52% - 60% of the total floor

0

Existing PV on previously certified project

NC-v4 EAc5:Renewable energy production
posted by  Yu Zhang  on 

I have a project that is a new building located on a previous certified LEED project with PV production.  The previous project had >90% offset by energy use and >100% offset by cost from

10
Wed Mar 6, 2024, 5:20 pm
2
Freelance LEED Coordinator
Construction Company
LEEDuser Basic Member
3 thumbs up
Wed Mar 6, 2024, 2:34 pm
2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Wed Mar 6, 2024, 9:21 am

50% surface area reuse

CI-v4.1 MRc2:Interiors Life-Cycle Impact Reduction
posted by  Mark Ragucci  on 

how is this credit calculated? can in include existing floor slab and deck? we are leaving a portion of the exiting walls that are about 20ft tall and our ceilings will be at 9'.

3
Project Architect
Jacobs
LEEDuser Premium Member
0 thumbs up
Wed Mar 6, 2024, 12:34 am

Backup Documentation

NC-v4 WEc4:Water metering
posted by  Michelle Rosenberger  on 

It seems that many credits no longer ask for any backup to be uploaded. Including this one. This lack makes us uncomfortable because we've always uploaded plans sheets.

2
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Tue Mar 5, 2024, 5:27 pm

Consideration of Manmade Ponds in Protect or Restore Habitat Credit Calculations.

NC-v4.1 SSc2:Protect or Restore Habitat
posted by  Subhashkumar A  on 

In one of our project, the site includes man-made ponds, which are used as rainwater storage ponds.

1
Mon Mar 4, 2024, 8:46 pm

What is the Exact Definition of A Trip?

NC-v4 LTc5:Access to quality transit
posted by  Krithikha Muthukrishnan  on 

I am posting this question largely because the credit langauage is not very clear(maybe language nativity issues here). In the Reference Guide, "A Trip" is defined as follows-

2
Mon Mar 4, 2024, 2:29 pm

Preheat coil requirement in baseline

NC-v4.1 EAp2:Minimum Energy Performance
posted by  Samer Hassanie  on 

Hi,

It is not clear from G3.1.3.19 where the preheat coil should be placed.

Is it upstream or downstream the economizer and the heat exchanger?

5
Mon Mar 4, 2024, 11:50 am