EAp2 Prescriptive Path- Renovation and Addition

NC-2009 EAp2:Minimum Energy Performance
posted by  Eric Elizondo  on 

EAp2- Option 2 Prescriptive Method The current project consists of an existing building that is being renovated along with a new addition to the building.

1
Wed Oct 17, 2012, 2:34 pm

Shampoo Bowls

Schools-2009 WEc3:Water Use Reduction
posted by  Ara Massey  on 

I am working on a vocational high school that has shampoo bowls in the cosmetology classroom. Do these fixtures need to be included in WEc3 and if so as what type of fixture? Thanks!

1
Wed Oct 17, 2012, 4:34 pm

For Assemblies - what is the location of extraction?

NC-2009 MRc5:Regional Materials
posted by  Melissa Wrolstad  on 

My client has a chair which was manufactured within 500 miles of the project site. The chair is composed of foam (5%), plastic (2%), wood (13%) and steel (80%) by weight.

1
Fri Nov 23, 2012, 5:41 am

Option 1 Zoning for a CI- Facility with out of scope areas withi

CI-2009 EAc1.3:Optimize Energy Performance—HVAC
posted by  Saju Varghese  on 

Good afternoon. We are currently submitting templates for a University facility.

1
Thu Oct 25, 2012, 1:53 pm

Formaldehyde Emissions in Plywood Cabinets

NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Products
posted by  Andy Kallam  on 

I am currently considering submitting a plywood product for cabinetry that does contain Urea Formaldehyde adhesives.

1
Thu Oct 18, 2012, 1:44 am

Millwork as a whole vs. each piece

NC-2009 MRc7:Certified Wood
posted by  Caro Wilbanks  on 

We have been denied the MR7 point on a couple of jobs becuase of the millwork documentation.

0

Bonus point for the Regional Priority Credits

EBOM-2009 RPc1:Regional Priority
posted by  Sundararaj Subburaman  on 

We browsed the USGBC website for Regional Priority Credits outside US in the following link: www.usgbc.org/DisplayPage.aspx?CMSPageID=2435 It is mentioned that earning up to four of the six credit

1
Thu Oct 18, 2012, 2:05 pm

custom-made refrigerator for EBOM project

NC-2009 EAp3:Fundamental Refrigerant Management
posted by  Jorng-ren Chern  on 

I am working on EBOM for an old office building which includes an employee cafeteria.

1
Thu Oct 18, 2012, 1:52 pm

1 Additional Bonus Point for earning all 4 RPCs

CI-2009 RPc1:Regional Priority
posted by  Nandana Kumar  on 

Hi, I wanted to understand if it is possible to earn 1 additional bonus points, if the project has earned all 4 points under the RPCs. or is the interpretation of earning only a maximum 4 RPCs

1
Thu Oct 18, 2012, 2:05 pm

scope of materials

CI-2009 MRc3.2:Materials Reuse—Furniture and Furnishings
posted by  Adam Targowski  on 

I would like to clarify what should be included in the calculations for this credit.

1
Thu Oct 25, 2012, 4:23 pm