Location of bicycle storage
CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Dean Barone on
We have a situation where the footprint of the site is too small to accommodate all of the required bicycle racks serving our project in one area.
Rental Laundry Supplied Entrance Mats
NC-2009 IEQc5:Indoor Chemical and Pollutant Source Controlposted by Charles Eichelberger on
I am new to Leed Requirements, and as my company manufactures walk-off mats, I am currently assisting one of our laundry rental customers in providing 10-ft, laundered entrance way walk-off mats to
ASHRAE 90.1 Add G table G3.1 baseline
CS-2009 EAc1:Optimize Energy Performanceposted by charles bell on
We have a building which is six stories. The first floor is retail, second thru fifth is office and sixth is residential. All are served from a virtual central plant.
EAC2 in a Positive Energy Building
NC-2009 EAc2:On-Site Renewable Energyposted by Milena Rafols Salvador on
We are certifying a Positive Energy Building, that will produce 130% of its energy consumption with solar PV. All the energy produced with the PV will be sold to the grid.
EAc5 Exemplary Performance
NC-2009 EAc5:Measurement and Verificationposted by Jodie Clarke on
The guidance for exemplary performance specifies the NC, CS and Schools rating systems. I would like to get credit for following Option 2 and 3 for Healthcare.
Retail FTEFull-time
CS-2009 WEp1:Water Use Reductionposted by James Wieben on
Retail FTE is for 8 hour shifts, so if the business has 12 hours open to the public do I use a value of 1.5 x the FTE value to arrive at a value to use when defining the usage of the plumbing fixtu
LEED for Home Multi-Family
Pilot-Credits PC38:Advanced Utility Trackingposted by Nate Gapinski on
Has anyone ever certified a multi-family construction project? Just wanted to see how the process was and if we are on top of everything.
Accessibility for Seniors
Pilot-Credits PC34:Design for Adaptabilityposted by Lance Hillegas on
Our project is an age and income restricted apartment building for low income seniors.
Outdoor Air Intake: Baseline vs. Proposed
NC-2009 EAp2:Minimum Energy Performanceposted by Ricardo Sá on
We are currently working on a LEED project whose Baseline Building will have an HVAC system 5 installed.
Distance between bicycle storage and building entrance
CS-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Roomsposted by Patricia Missawa on
According to LEED Commercial Interiors SSc3.2 - Alternative Transportation: Bicycle storage and changing rooms template, if a bicycle storage is located within the building, the distance must be co