Forum quick links
Exterior Walls and Ceiling Furred Out
NC-2009 MRc1.2:Building Reuse—Maintain Existing Interior Nonstructural Elementsposted by Sallyann Kluz on
We have an existing building that lacked insulation in exterior walls as well as the ceiling.
Hardscape
NC-2009 PIf2:Project Summary Detailsposted by Chris DeVolder on
Hi all, Thanks for the comments/feedback above. We have a small playing field/recreation field within our boundary adjacent to our building.
Manufacturing and Public Transit
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Andrew Sheridan on
We are working towards achieving this credit for a large manufacturing facility that runs 24 hours a day with 3 manufacturing shifts.
Feedback for ACP Program
Pilot-Credits EApc67:Energy Jumpstartposted by Elizabeth Crenshaw Hammitt on
Hi there LEED community, Our project team has just wrapped the performance period, and we are in the process of gathering documents and plan to submit our application in one week.
LEED Site Boundary
Healthcare-v2009 MPR3:Must use a reasonable site boundaryposted by Heather Holdridge on
We are working on a Core & Shell project and our LEED site boundary includes a large parking lot and landscape area along with the building on the plot.
Native or adapted vegetation area calculation
EBOM-2009 SSc5:Site Development—Protect or Restore Open Habitatposted by Sofia Otterheim on
Hi Everyone According to 2009 version LEED reference guide there are two ways to calculate out native or adapted vegetation area.
Tons vs Yards
CS-2009 MRc2:Construction Waste Managementposted by Kevin Short on
My waste hauler has given receipts in both tons and yards. I am using tons for the credit, is there some conversion factor I can use? The receipts in question are for landfill and wood.
Local Code more stringent than Ashrae 62.1
NC-2009 IEQp1:Minimum IAQ Performanceposted by Gaston Viau on
Our project has to achieve CA Title 24 which is more stringent than Ashrae 62.1.
Question
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Mario Leonhardt on
Can the LEED-CI certificate be obtained even after the renovation process has been completed? There has been no registrations or whatsoever before the renovation/construction.
VOC as an emission (%) vs Volume (g/L)
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Timothy Nabholz on
I was wondering if any of you have heard of others in Europe who have had trouble with meeting the SCAQMD requirements that LEED asks for in IEQ Credit 4.1 and 4.2.