Forum quick links
Type 1B Multi-family
NC-2009 IEQp2:Environmental Tobacco Smoke (ETS) Controlposted by Jeremy Kuhre on
Has anyone successfully pursued Option 2 Case 2 (blower door testing) for type 1B multi-family project?
Data Center Energy Calculator Tool
Data-Centers-NC-v4 EAc2:Optimize energy performanceposted by Jack Jenkins on
Does anybody have any experience with this new tool or know whether any further guidance on how it should be used is available? I have two questions in particular: 1) How is the baseline electrica
Addition Project Boundary remote from existing parking
Schools-NC-v4 MPR2:Must use reasonable LEED boundariesposted by Larry Turbes on
We are planning on certifying a school addition. The existing building is not certified and there will be a clear boundary between the addition and existing building.
Option 2: ASHRAE 90.1-2007 Section 11?
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Steve Gross on
Even though the credit language does not state it explicitly, I read "reduce design energy cost compared with the energy cost budget for regulated energy components" to mean "reduce the design ener
Humidity
EBOM-2009 EAc3.1:Performance Measurement—Building Automation Systemposted by Gustavo De las Heras Izquierdo on
I was wondering if there is a minimum set of comfort parameters which HAVE TO be measured by the BAS.
Variable Frequency Drive / Frequency convertors
CS-2009 IEQc1:Outdoor Air Delivery Monitoringposted by Petra Hajná on
Hello everybody. I have a question: Is installation of fan motors with variable frequency drive in main AHUs an acceptable option of outdoor air measurement? I went through credit interpretations,
Water feature
CS-2009 WEc1:Water Efficient Landscapingposted by Heather Holdridge on
If there is a water feature in the landscape, that is counted within this credit, correct?
ABOUT THIS FORUM
NC-2009 PIf1:Minimum Program Requirementsposted by Tristan Roberts on
This LEEDuser forum is intended to cover Project Information Form 1, which is about documenting compliance with the MPRs.
Meter Calibration
EBOM-2009 WEc1:Water Performance Measurementposted by Vincent Maglio on
Finding very difficult to get manufacturer recommended calibration intervals. Is there a code or governing body that can be used as a guide such as NSF or AWWA
EAp2 Labeling Mechanical Equipment
NC-2009 EAp2:Minimum Energy Performanceposted by Ian McCall on
Hello, Fact or Fiction: For EAp2 ASHRAE 90.1 §6.4.1.5.1 all mechanical Equipment must have a Label installed by the manufacturer stating that the equipment complies with the requirements of Standa