Late involvement by CxA.

CI-2009 EAc2:Enhanced Commissioning
posted by  Charles Nepps  on 

The Owner dragged his feet and did not bring a Commissioning Agent on board until after the construction documents were complete, and construction started.

1
Tue Mar 25, 2014, 7:45 pm

Hotel key tag system

NC-2009 EAp2:Minimum Energy Performance
posted by  Nandana Kumar  on 

We are working on a hotel project. The guest rooms have a key tag system where the lights and AC switches off as soon as the guest removes the key from the key slot.

1
Tue Mar 25, 2014, 2:36 pm

LEED Project Boundary for Site Prepped by Previous Project

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Cassandra Coffin  on 

I am working on a new residence hall for a college campus and have a couple of questions in regards to the LEED project boundary. Due to multiple scheduling impacts, the site work and deep foundat

0

M&V plan for cold and dark shell

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Jatuwat Varodompun  on 

In case the system is yet designed, can CS project get the score in 5.1 and 5.2 by purely using tanant leasing agreement which has the M&V Plan as a reguirement to be responsible by tenants.

1
Tue Mar 25, 2014, 4:18 pm

Breakdown of energy use

EBOM-2009 EAc2.1:Existing Building Commissioning—Investigation and Analysis
posted by  Gustavo De las Heras Izquierdo  on 

It is required by the credit: "to document the breakdown of energy use in the building". Is it mandatory to have permanent energy meters by end use in order to meet this requirement? What other m

1
Tue Mar 25, 2014, 6:05 pm

Exemplary Performance Compliance

NC-2009 SSc4.4:Alternative Transportation—Parking Capacity
posted by  Eddie Cuevas  on 

I am currently working on a nonresidential project on a college campus that is seeking to obtain an EP point by implementing parking for high-occupancy vehicles.

1
Fri Jul 25, 2014, 5:24 am

developer owned design build project

NC-2009 EAc3:Enhanced Commissioning
posted by  Chris Flint Chatto  on 

We are working on a design-build team developing a project that will be leased to a government agency.

1
Wed Apr 2, 2014, 1:51 pm

Sensor Type Flush Fixtures

CI-2009 WEc1:Water Use Reduction
posted by  Katherine Ann Resurreccion  on 

Hi Would Sensor activated flush fixtures like urinals and WCs have the same flow rate calulations as a sensor type flow fixture? Would it follow the default 12sec / 60 cycle?

1
Wed Mar 26, 2014, 12:31 pm

Not Regularly occupied

NC-v4 EQc1:Enhanced indoor air quality strategies
posted by  Phillip Cook  on 

In LEED v2009, if a project has less than 1 annualized FTE occupancy it was not possible to achieve any of the IEQ points.

1
Wed Aug 6, 2014, 4:10 pm

Car park in basement

CS-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Mike D  on 

If only four car parking spaces are located within the basement of the building, will they require separate exhaust even if they are not used regularly?

0