Development Radius for EP
NC-2009 SSc2:Development Density and Community Connectivityposted by Robert Celio on
We have a project in the city and can easily meet the EP requirements for Option 1.
Option 1: Existing Equipment
CI-2009 EAc1.3:Optimize Energy Performance—HVACposted by Steve Gross on
I have read Interpretation #10134 and 10135, but based on some of the comments below, I would like some additional confirmation.
Naturally ventilated and heated warehouse
NC-2009 IEQc7.1:Thermal Comfort—Designposted by Scott McMillan on
We seek some advice on how to demonstrate thermal comfort compliance for occupied spaces in an industrial warehouse type space in Christchurch, New Zealand.
Historic building.... in progress
ND-v2009 GIBc6:Historic resource preservation and adaptive useposted by Colin Inderwish on
Hello, We have a 100 yr old masonry chapel on our site that we are in the process of registering as a historic building. The process takes several months to a year.
acrylic with non paper backer
Homes-v4 MRp2:Durability managementposted by Elizabeth Eason on
The credit calls for non paper faced backer board behind fiberglass enclosures. Does that apply to behind acrylic surrounds also?
Baseline confussion
EBOM-2009 WEp1:Minimum Indoor Plumbing Fixture and Fitting Efficiencyposted by Mohamed Hesham on
i want to know what is the differences between the ipc baseline calculations ,the LEED EBOM baseline and the performance calculation, in the case i'm dealing with the building fixtures already comp
LEED Canada Option 3 Public & Catholic Joint Use School
NC-2009 SSc4.1:Alternative Transportation—Public Transportation Accessposted by Kelly Searle on
We are building a joint use school and trying to determine the likelihood of achieving 3 credits under SSc4.1 Alternative Transportation: Public Transportation Access - Option 3 (Transportation Dem
The difference of Reused, Salvaged, refurbished
NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materialsposted by Qiang Zhang on
As posted for Materials reuse.
Tables titles missing
ND-v2009 SLLp4:Agricultural land conservationposted by Andres Schwarz on
On the SSLp4 Credit Language section, the titles of the tables are missing.
how long can be interval time between 2 parts of projects
CS-2009 MPR2:Must be a complete, permanent building or spaceposted by Catharina B on
Hello We are working on the project, which include 3 independent buildings: A, B & C – but for certification is one single building (each 17 stories above grade has own mechanic, energy system